ITAC Assessment: BS0063
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2015
Principal Product Structural Steel
NAICS 332312: Fabricated Structural Metal Manufacturing
SIC 3441: Fabricated Structural Metal
Sales Range $10
M
to 50
M
# of Employees 45
Plant Area 44,400
ft2
Annual Production 700,000
lb
Production Hrs. Annual 6,240
hrs
Location (State) Idaho

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $39,288 643,720
kWh
Electricity Demand $21,875 4,284
kW-mo/yr
Electricity Fees $822 -
Natural Gas $20,332 2,784
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $17,627 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $6,912

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.4111: Utilize energy-efficient belts and other improved mechanisms $260 $208 $260
4,260
kWh
-
02 2.2437: Recover waste heat from equipment $7,981 $3,759 - $7,981
-
MMBtu
03 2.7135: Install occupancy sensors $143 $357 $143
2,342
kWh
-
04 2.4221: Install compressor air intakes in coolest locations $1,150 $1,124 $1,150
18,857
kWh
-
05 2.4235: Remove or close off unneeded compressed air lines $3,476 $12,265 $3,476
56,959
kWh
-
06 2.2492: Use "heat wheel" or other heat exchanger to cross-exchange building exhaust air with make-up air $2,734 $2,453 - $2,734
-
MMBtu
07 2.7221: Lower temperature during the winter season and vice-versa $1,883 $503 $42
690
kWh
$1,841
-
MMBtu
TOTAL RECOMMENDED $17,627 $20,669 $5,071
83,108
kWh
$12,556
-
MMBtu
TOTAL IMPLEMENTED $6,912 $14,457 $5,071
83,108
kWh
$1,841
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs