| Assessment Year | 2015 |
|---|---|
| Principal Product | Structural Steel |
| NAICS | 332312: Fabricated Structural Metal Manufacturing |
| SIC | 3441: Fabricated Structural Metal |
| Sales Range | $10 M to 50M |
| # of Employees | 45 |
| Plant Area |
44,400
ft2
|
| Annual Production | 700,000
lb
|
| Production Hrs. Annual | 6,240
hrs
|
| Location (State) | Idaho |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $39,288 | 643,720 |
kWh
|
$0.061 |
| Electricity Demand | $21,875 | 4,284 |
kW-mo/yr
|
$5.11 |
| Electricity Fees | $822 | - |
|
- |
| Natural Gas | $20,332 | 2,784 |
MMBtu
|
$7.30 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $17,627 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $6,912 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|
| 01 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $260 | $208 |
$260
4,260
kWh
|
- | |
| 02 | 2.2437: Recover waste heat from equipment | $7,981 | $3,759 | - |
$7,981
-
MMBtu
|
|
| 03 | 2.7135: Install occupancy sensors | $143 | $357 |
$143
2,342
kWh
|
- | |
| 04 | 2.4221: Install compressor air intakes in coolest locations | $1,150 | $1,124 |
$1,150
18,857
kWh
|
- | |
| 05 | 2.4235: Remove or close off unneeded compressed air lines | $3,476 | $12,265 |
$3,476
56,959
kWh
|
- | |
| 06 | 2.2492: Use "heat wheel" or other heat exchanger to cross-exchange building exhaust air with make-up air | $2,734 | $2,453 | - |
$2,734
-
MMBtu
|
|
| 07 | 2.7221: Lower temperature during the winter season and vice-versa | $1,883 | $503 |
$42
690
kWh
|
$1,841
-
MMBtu
|
|
| TOTAL RECOMMENDED | $17,627 | $20,669 |
$5,071
83,108
kWh
|
$12,556
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $6,912 | $14,457 |
$5,071
83,108
kWh
|
$1,841
-
MMBtu
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs