ITAC Assessment: SU0576
ITAC logo
ITAC Assessment: SU0576
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2025
Principal Product Cider and bottling pasteurizing, process cleaning
NAICS 445299: All Other Specialty Food Stores
SIC 2086: Bottled and Canned Soft Drinks and Carbonated Waters
Sales Range $10
M
to 50
M
# of Employees 90
Plant Area 165,000
ft2
Annual Production 7,000,000
units
Production Hrs. Annual 8,760
hrs
Location (State) New York

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $200,490 5,208,487
kWh
Electricity Demand $319,530 11,616
kW-mo/yr
Electricity Fees $11,711 -
Natural Gas $417,833 79,128
MMBtu
LPG $5,288 2,931
MMBtu
Other Gas $10,699 1
MMBtu
TOTAL YEARLY COSTS $965,551
RECOMMENDED SAVINGS* $122,265 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings One-time Revenue or Avoided Cost Savings
01 2.3131: Reschedule plant operations or reduce load to avoid peaks $15,976 - - $15,976
-
kW-mo/yr
- -
02 2.4231: Reduce the pressure of compressed air to the minimum required $4,743 - $4,743
124,822
kWh
- - -
03 2.4322: Use or replace with energy efficient substitutes $472 $18 $145
3,825
kWh
$413
-
kW-mo/yr
$(-86.1)
-
MMBtu
-
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,295 $125 $1,295
34,075
kWh
- - -
05 2.4221: Install compressor air intakes in coolest locations $2,825 $372 $2,825
74,346
kWh
- - -
06 2.2511: Insulate bare equipment $1,088 $728 - - $1,088
-
MMBtu
-
07 2.7142: Utilize higher efficiency lamps and/or ballasts $23,941 $17,246 $1,629
42,873
kWh
$2,062
-
kW-mo/yr
- $20,250
08 2.2135: Repair and eliminate steam leaks $3,215 $2,800 - - $3,215
-
MMBtu
-
09 2.4322: Use or replace with energy efficient substitutes $287 $403 $80
2,102
kWh
$79
-
kW-mo/yr
- $128
10 2.6211: Conserve energy by efficient use of vending machines $221 $899 $221
5,825
kWh
- - -
11 4.631: Install an uninteruptable power supply $35,256 $160,000 - - - $35,256
12 2.9114: Use solar heat to make electricty $32,946 $668,352 $32,946
867,000
kWh
- - -
TOTAL RECOMMENDED $122,265 $850,943 $43,885
1,154,868
kWh
$18,530
-
kW-mo/yr
$4,217
-
MMBtu
$55,634
TOTAL IMPLEMENTED - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings One-time Revenue or Avoided Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs