Assessment Year | 1998 |
---|---|
Principal Product | Coolant Reservoirs |
NAICS |
n/a
|
SIC | 2789: Bookbinding and Related Work |
Sales Range | $5 M to 10M |
# of Employees | 100 |
Plant Area |
50,000
ft2
|
Annual Production | 5,500,000
units
|
Production Hrs. Annual | 6,336
hrs
|
Location (State) | Michigan |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $94,300 | 2,760,258 |
kWh
|
$0.034 |
Electricity Demand | $57,890 | 6,516 |
kW-mo/yr
|
$8.88 |
Natural Gas | $7,220 | 1,715 |
MMBtu
|
$4.21 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $50,560 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Water Disposal Savings | Solid Waste (non-haz) Savings | Primary Product Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.4133: Use most efficient type of electric motors | $866 | $1,540 | n/a |
$604
17,878
kWh
|
$262
-
kW-mo/yr
|
- | - | - |
02 | 2.4221: Install compressor air intakes in coolest locations | $727 | $1,000 | n/a |
$679
13,482
kWh
|
$48
-
kW-mo/yr
|
- | - | - |
03 | 3.5316: Contract a wood pallet recycling company | $3,250 | $100 | n/a | - | - | - |
$3,250
-
lb
|
- |
04 | 3.4111: Use closed cycle process to minimize waste water production | $1,804 | $1,580 | n/a | - | - |
$1,804
-
Tgal
|
- | - |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $16,065 | $9,154 | n/a | - | - | - | - | $16,065 |
06 | 4.631: Install an uninteruptable power supply | $27,848 | $10,800 | n/a | - | - | - | - | $27,848 |
TOTAL RECOMMENDED | $50,560 | $24,174 |
$1,283
31,360
kWh
|
$310
-
kW-mo/yr
|
$1,804
-
Tgal
|
$3,250
-
lb
|
$43,913 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Water Disposal Savings | Solid Waste (non-haz) Savings | Primary Product Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs