Assessment Year | 2006 |
---|---|
Principal Product | fire rescue vehicles |
NAICS | 332999: All Other Miscellaneous Fabricated Metal Product Manufacturing |
SIC | 3499: Fabricated Metal Products, Not Elsewhere Classified |
Sales Range | $50 M to 100M |
# of Employees | 242 |
Plant Area |
78,500
ft2
|
Annual Production | 120
units
|
Production Hrs. Annual | 5,070
hrs
|
Location (State) | Florida |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $220,741 | 2,717,100 |
kWh
|
$0.081 |
Electricity Demand | $49,269 | 7,503 |
kW-mo/yr
|
$6.57 |
Natural Gas | $49,153 | 3,102 |
MMBtu
|
$15.85 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $37,252 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,441 | $4,440 |
$3,725
45,995
kWh
|
$716
-
kW-mo/yr
|
- | - | - | |
02 | 2.7131: Add area lighting switches | $5,721 | $13,094 |
$5,721
70,634
kWh
|
- | - | - | - | |
03 | 2.7124: Make a practice of turning off lights when not needed | $1,878 | - |
$1,878
23,188
kWh
|
- | - | - | - | |
04 | 2.7111: Reduce illumination to minimum necessary levels | $1,880 | $56 |
$1,577
19,469
kWh
|
$303
-
kW-mo/yr
|
- | - | - | |
05 | 2.7135: Install occupancy sensors | $1,101 | $1,703 |
$1,101
13,596
kWh
|
- | - | - | - | |
06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $12,727 | $1,457 |
$12,727
128,551
kWh
|
- | - | - | - | |
07 | 2.6218: Turn off equipment when not in use | $811 | - |
$811
10,012
kWh
|
- | - | - | - | |
08 | 2.4239: Eliminate or reduce compressed air usage | $711 | - |
$711
7,178
kWh
|
- | - | - | - | |
09 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $212 | - |
$97
986
kWh
|
- | - | $42 | $73 | |
10 | 2.7292: Lower ceiling to reduce conditioned space | $4,883 | $846 | - | - |
$4,883
-
MMBtu
|
- | - | |
11 | 2.7232: Replace existing hvac unit with high efficiency model | $2,887 | $24,500 |
$2,154
26,598
kWh
|
$733
-
kW-mo/yr
|
- | - | - | |
TOTAL RECOMMENDED | $37,252 | $46,096 |
$30,502
346,207
kWh
|
$1,752
-
kW-mo/yr
|
$4,883
-
MMBtu
|
$42 | $73 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs