ITAC Assessment: UF0386
ITAC logo
ITAC Assessment: UF0386
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2006
Principal Product fire rescue vehicles
NAICS 332999: All Other Miscellaneous Fabricated Metal Product Manufacturing
SIC 3499: Fabricated Metal Products, Not Elsewhere Classified
Sales Range $50
M
to 100
M
# of Employees 242
Plant Area 78,500
ft2
Annual Production 120
units
Production Hrs. Annual 5,070
hrs
Location (State) Florida

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $220,741 2,717,100
kWh
Electricity Demand $49,269 7,503
kW-mo/yr
Natural Gas $49,153 3,102
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $37,252 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Ancillary Material Cost Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $4,441 $4,440 $3,725
45,995
kWh
$716
-
kW-mo/yr
- - -
02 2.7131: Add area lighting switches $5,721 $13,094 $5,721
70,634
kWh
- - - -
03 2.7124: Make a practice of turning off lights when not needed $1,878 - $1,878
23,188
kWh
- - - -
04 2.7111: Reduce illumination to minimum necessary levels $1,880 $56 $1,577
19,469
kWh
$303
-
kW-mo/yr
- - -
05 2.7135: Install occupancy sensors $1,101 $1,703 $1,101
13,596
kWh
- - - -
06 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $12,727 $1,457 $12,727
128,551
kWh
- - - -
07 2.6218: Turn off equipment when not in use $811 - $811
10,012
kWh
- - - -
08 2.4239: Eliminate or reduce compressed air usage $711 - $711
7,178
kWh
- - - -
09 2.4111: Utilize energy-efficient belts and other improved mechanisms $212 - $97
986
kWh
- - $42 $73
10 2.7292: Lower ceiling to reduce conditioned space $4,883 $846 - - $4,883
-
MMBtu
- -
11 2.7232: Replace existing hvac unit with high efficiency model $2,887 $24,500 $2,154
26,598
kWh
$733
-
kW-mo/yr
- - -
TOTAL RECOMMENDED $37,252 $46,096 $30,502
346,207
kWh
$1,752
-
kW-mo/yr
$4,883
-
MMBtu
$42 $73
TOTAL IMPLEMENTED - - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs