Assessment Year | 1997 |
---|---|
Principal Product | Fiberglass reinforced products |
NAICS |
n/a
|
SIC | 3070: |
Sales Range | $1 M to 5M |
# of Employees | 41 |
Plant Area |
38,000
ft2
|
Annual Production | 350
ton
|
Production Hrs. Annual | 2,470
hrs
|
Location (State) | Michigan |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $22,728 | 518,171 |
kWh
|
$0.044 |
Electricity Demand | $27,619 | 2,388 |
kW-mo/yr
|
$11.57 |
Electricity Fees | $606 | - |
|
- |
Natural Gas | $19,064 | 4,926 |
MMBtu
|
$3.87 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $30,203 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $3,525 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Primary Product Savings |
---|---|---|---|---|---|---|---|
01 | 2.4133: Use most efficient type of electric motors | $364 | $5,910 |
$152
3,517
kWh
|
$212
-
kW-mo/yr
|
- | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,225 | $10,986 |
$1,327
30,188
kWh
|
$1,898
-
kW-mo/yr
|
- | |
03 | 2.4221: Install compressor air intakes in coolest locations | $939 | $480 |
$566
5,862
kWh
|
$373
-
kW-mo/yr
|
- | |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,222 | $700 |
$2,222
23,447
kWh
|
- | - | |
05 | 4.121: Maintain clean conditions before painting | $23,453 | $15,000 | - | - | $23,453 | |
TOTAL RECOMMENDED | $30,203 | $33,076 |
$4,267
63,014
kWh
|
$2,483
-
kW-mo/yr
|
$23,453 | ||
TOTAL IMPLEMENTED | $3,525 | $7,090 |
$2,940
32,826
kWh
|
$585
-
kW-mo/yr
|
- |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs