ITAC Assessment: UM0092
ITAC logo
ITAC Assessment: UM0092
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1997
Principal Product Potato Products
NAICS
n/a
SIC 2037: Frozen Fruits, Fruit Juices, and Vegetables
Sales Range $10
M
to 50
M
# of Employees 220
Plant Area 214,307
ft2
Annual Production 114,000,000
lb
Production Hrs. Annual 7,056
hrs
Location (State) Michigan

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $624,095 17,648,887
kWh
Electricity Demand $84,811 36,084
kW-mo/yr
Electricity Fees $145,562 -
Natural Gas $601,098 196,529
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $297,606 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Administrative Changes Savings Primary Product Savings
01 2.4133: Use most efficient type of electric motors $4,141 $4,497 $2,276
77,081
kWh
$1,865
-
kW-mo/yr
- - -
02 2.7142: Utilize higher efficiency lamps and/or ballasts $6,616 $29,553 $3,927
145,369
kWh
$2,689
-
kW-mo/yr
- - -
03 2.4221: Install compressor air intakes in coolest locations $696 $1,000 $382
12,896
kWh
$314
-
kW-mo/yr
- - -
04 2.2523: Reduce infiltration to refrigerated areas; isolate hot equipment from refrigerated areas $35,249 $8,500 $25,096
760,844
kWh
$10,153
-
kW-mo/yr
- - -
05 2.2511: Insulate bare equipment $1,392 $5,361 - - $1,392
-
MMBtu
- -
06 3.6112: Use filter and drying oven to reduce sludge volume $245,000 $10,000 - - - $245,000 -
07 4.652: Replace existing equipment with more suitable substitutes $4,512 $300 - - - - $4,512
TOTAL RECOMMENDED $297,606 $59,211 $31,681
996,190
kWh
$15,021
-
kW-mo/yr
$1,392
-
MMBtu
$245,000 $4,512
TOTAL IMPLEMENTED - - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Administrative Changes Savings Primary Product Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs