Assessment Year | 1997 |
---|---|
Principal Product | Printed forms and envelopes |
NAICS |
n/a
|
SIC | 2752: Commercial Printing, Lithographic |
Sales Range | $10 M to 50M |
# of Employees | 160 |
Plant Area |
51,000
ft2
|
Annual Production | 5,000,000
lb
|
Production Hrs. Annual | 6,864
hrs
|
Location (State) | Michigan |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $143,030 | 2,315,065 |
kWh
|
$0.062 |
Electricity Demand | $55,210 | 5,867 |
kW-mo/yr
|
$9.41 |
Electricity Fees | $8,662 | - |
|
- |
Natural Gas | $12,822 | 3,000 |
MMBtu
|
$4.27 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $60,184 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $24,588 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Other Liquid (haz) Savings | Personnel Changes Savings | Primary Raw Material Savings | Primary Product Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.4133: Use most efficient type of electric motors | $7,640 | $7,640 |
$5,698
118,113
kWh
|
$1,942
-
kW-mo/yr
|
- | - | - | - | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $23,988 | $23,988 |
$19,329
196,366
kWh
|
$4,659
-
kW-mo/yr
|
- | - | - | - | |
03 | 2.4221: Install compressor air intakes in coolest locations | $600 | $600 |
$521
3,224
kWh
|
$79
-
kW-mo/yr
|
- | - | - | - | |
04 | 3.5121: Recycle waste ink and cleanup solvent | $1,270 | $5,080 | - | - |
$718
-
gal
|
$(-472.0) | $1,024 | - | |
05 | 2.7243: Improve air circulation with destratification fans / other methods | $26,686 | $1,500 | - | - | - | - | - | $26,686 | |
TOTAL RECOMMENDED | $60,184 | $38,808 |
$25,548
317,703
kWh
|
$6,680
-
kW-mo/yr
|
$718
-
gal
|
$(-472.0) | $1,024 | $26,686 | ||
TOTAL IMPLEMENTED | $24,588 | $24,588 |
$19,850
199,590
kWh
|
$4,738
-
kW-mo/yr
|
- | - | - | - |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs