Assessment Year | 1996 |
---|---|
Principal Product | Automotive Stampings and Assembly |
NAICS |
n/a
|
SIC | 3469: Metal Stampings, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 250 |
Plant Area |
80,000
ft2
|
Annual Production | 60,000,000
pieces
|
Production Hrs. Annual | 7,344
hrs
|
Location (State) | Michigan |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $346,068 | 11,443,435 |
kWh
|
$0.030 |
Electricity Demand | $338,023 | 28,706 |
kW-mo/yr
|
$11.78 |
Electricity Fees | $38,942 | - |
|
- |
Natural Gas | $28,674 | 6,758 |
MMBtu
|
$4.24 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $44,263 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $3,147 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Solid Waste (non-haz) Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.4133: Use most efficient type of electric motors | $1,573 | $3,037 |
$1,007
33,998
kWh
|
$566
-
kW-mo/yr
|
- | - | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $885 | $3,074 |
$338
11,430
kWh
|
$547
-
kW-mo/yr
|
- | - | |
03 | 2.3212: Optimize plant power factor | $21,041 | $15,570 | - |
$16,339
-
kW-mo/yr
|
$4,702 | - | |
04 | 2.4221: Install compressor air intakes in coolest locations | $689 | $1,200 |
$441
14,947
kWh
|
$248
-
kW-mo/yr
|
- | - | |
05 | 2.4314: Use synthetic lubricant | $830 | $960 |
$531
17,878
kWh
|
$299
-
kW-mo/yr
|
- | - | |
06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $10,326 | - |
$6,611
223,329
kWh
|
$3,715
-
kW-mo/yr
|
- | - | |
07 | 2.3132: Recharge batteries on during off-peak demand periods | $5,439 | $24,000 | - |
$5,439
-
kW-mo/yr
|
- | - | |
08 | 3.5248: Separate and recycle scrap metal to foundry or for sale | $3,480 | $1,200 | - | - | - |
$3,480
-
lb
|
|
TOTAL RECOMMENDED | $44,263 | $49,041 |
$8,928
301,582
kWh
|
$27,153
-
kW-mo/yr
|
$4,702 |
$3,480
-
lb
|
||
TOTAL IMPLEMENTED | $3,147 | $7,311 |
$1,786
60,375
kWh
|
$1,361
-
kW-mo/yr
|
- | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Solid Waste (non-haz) Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs