Assessment Year | 1996 |
---|---|
Principal Product | Aluminum Extrusions |
NAICS |
n/a
|
SIC | 3354: Aluminum Extruded Products |
Sales Range | $10 M to 50M |
# of Employees | 50 |
Plant Area |
150,000
ft2
|
Annual Production | 9,000,000
lb
|
Production Hrs. Annual | 2,295
hrs
|
Location (State) | Michigan |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $64,046 | 1,727,433 |
kWh
|
$0.037 |
Electricity Demand | $85,998 | 9,807 |
kW-mo/yr
|
$8.77 |
Natural Gas | $49,227 | 13,008 |
MMBtu
|
$3.78 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $31,766 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Primary Raw Material Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.4133: Use most efficient type of electric motors | $244 | $2,260 |
$165
1,758
kWh
|
$79
-
kW-mo/yr
|
- | - | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $13,678 | $18,091 |
$11,598
133,353
kWh
|
$2,080
-
kW-mo/yr
|
- | - | |
03 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $3,369 | $305 |
$2,294
26,377
kWh
|
$1,075
-
kW-mo/yr
|
- | - | |
04 | 2.4221: Install compressor air intakes in coolest locations | $2,341 | $1,000 |
$1,988
22,860
kWh
|
$353
-
kW-mo/yr
|
- | - | |
05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,611 | $350 |
$3,069
35,463
kWh
|
$542
-
kW-mo/yr
|
- | - | |
06 | 2.7231: Use radiant heater for spot heating | $2,480 | $5,100 | - | - |
$2,480
-
MMBtu
|
- | |
07 | 3.5311: Recover and reuse waste material | $6,043 | - | - | - | - | $6,043 | |
TOTAL RECOMMENDED | $31,766 | $27,106 |
$19,114
219,811
kWh
|
$4,129
-
kW-mo/yr
|
$2,480
-
MMBtu
|
$6,043 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Primary Raw Material Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs