| Assessment Year | 1994 |
|---|---|
| Principal Product | Pickling and slitting |
| NAICS |
n/a
|
| SIC | 3399: Primary Metal Products, Not Elsewhere Classified |
| Sales Range | $10 M to 50M |
| # of Employees | 100 |
| Plant Area |
250,000
ft2
|
| Annual Production | 600,000
ton
|
| Production Hrs. Annual | 8,400
hrs
|
| Location (State) | Michigan |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Natural Gas | $312,215 | 117,773 |
MMBtu
|
$2.65 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $33,224 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $32,811 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|
| 01 | 2.4133: Use most efficient type of electric motors | $12,087 | $19,430 | - |
$12,087
-
MMBtu
|
|
| 02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $11,226 | $15,513 | - |
$11,226
-
MMBtu
|
|
| 03 | 2.4226: Use / purchase optimum sized compressor | $4,498 | $16,200 | - |
$4,498
-
MMBtu
|
|
| 04 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $5,000 | - |
$5,000
-
kWh
|
- | |
| 05 | 2.2414: Use waste heat from hot flue gases to preheat | $413 | $350 | - |
$413
-
MMBtu
|
|
| TOTAL RECOMMENDED | $33,224 | $51,493 |
$5,000
-
kWh
|
$28,224
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $32,811 | $51,143 |
$5,000
-
kWh
|
$27,811
-
MMBtu
|
||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs