| Assessment Year | 2024 |
|---|---|
| Principal Product | Fireproof Logs |
| NAICS | 327390: Other Concrete Product Manufacturing |
| SIC | 3297: Nonclay Refractories |
| Sales Range | $10 M to 50M |
| # of Employees | 180 |
| Plant Area |
144,530
ft2
|
| Annual Production | 173,037
units
|
| Production Hrs. Annual | 2,040
hrs
|
| Location (State) | Kentucky |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $68,881 | 1,737,740 |
kWh
|
$0.040 |
| Electricity Demand | $221,566 | 11,274 |
kW-mo/yr
|
$19.65 |
| Electricity Fees | $37,948 | - |
|
- |
| Natural Gas | $138,938 | 24,203 |
MMBtu
|
$5.74 |
| TOTAL YEARLY COSTS | $467,333 | |||
| RECOMMENDED SAVINGS* | $123,802 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.9114: Use solar heat to make electricty | $76,606 | $698,579 |
$40,986
1,033,991
kWh
|
$35,620
-
kW-mo/yr
|
- | |
| 02 | 2.7221: Lower temperature during the winter season and vice-versa | $746 | $2,700 |
$160
4,035
kWh
|
- |
$586
-
MMBtu
|
|
| 03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,717 | $1,995 |
$1,717
43,352
kWh
|
- | - | |
| 04 | 2.1121: Use insulation in furnaces to facilitate heating / cooling | $4,053 | $13,653 | - | - |
$4,053
-
MMBtu
|
|
| 05 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $5,372 | $5,000 | - |
$5,372
-
kW-mo/yr
|
- | |
| 06 | 2.2414: Use waste heat from hot flue gases to preheat | $35,308 | $50,000 | - | - |
$35,308
-
MMBtu
|
|
| TOTAL RECOMMENDED | $123,802 | $771,927 |
$42,863
1,081,378
kWh
|
$40,992
-
kW-mo/yr
|
$39,947
-
MMBtu
|
||
| TOTAL IMPLEMENTED | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs