| Assessment Year | 2000 |
|---|---|
| Principal Product | Lithographic Printed Material |
| NAICS |
n/a
|
| SIC | 2752: Commercial Printing, Lithographic |
| Sales Range | $5 M to 10M |
| # of Employees | 100 |
| Plant Area |
100,000
ft2
|
| Annual Production | 5,000,000
lb
|
| Production Hrs. Annual | 7,200
hrs
|
| Location (State) | Kentucky |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $68,561 | 2,187,866 |
kWh
|
$0.031 |
| Electricity Demand | $57,114 | 6,400 |
kW-mo/yr
|
$8.92 |
| Natural Gas | $770 | 144 |
MMBtu
|
$5.35 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $31,156 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | One-time Revenue or Avoided Cost Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,062 | $20 |
$729
23,154
kWh
|
$333
-
kW-mo/yr
|
- | - | |
| 02 | 2.4221: Install compressor air intakes in coolest locations | $220 | $44 |
$151
4,689
kWh
|
$69
-
kW-mo/yr
|
- | - | |
| 03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $6,128 | $20,707 |
$4,169
133,353
kWh
|
$1,959
-
kW-mo/yr
|
- | - | |
| 04 | 3.5248: Separate and recycle scrap metal to foundry or for sale | $121 | - | - | - |
$121
-
lb
|
- | |
| 05 | 4.453: Reschedule breaks to allow for continuous production | $23,625 | $2,500 | - | - | - | $23,625 | |
| TOTAL RECOMMENDED | $31,156 | $23,271 |
$5,049
161,196
kWh
|
$2,361
-
kW-mo/yr
|
$121
-
lb
|
$23,625 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs