| Assessment Year | 1999 |
|---|---|
| Principal Product | Fabricated wire and metal parts |
| NAICS |
n/a
|
| SIC | 3357: Drawing and Insulating of Nonferrous Wire |
| Sales Range | $10 M to 50M |
| # of Employees | 96 |
| Plant Area |
55,000
ft2
|
| Annual Production | 7,500,000
pieces
|
| Production Hrs. Annual | 6,336
hrs
|
| Location (State) | Kentucky |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $94,480 | 2,828,839 |
kWh
|
$0.033 |
| Electricity Demand | $12,425 | 6,666 |
kW-mo/yr
|
$1.86 |
| Natural Gas | $15,000 | 3,735 |
MMBtu
|
$4.02 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $19,432 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $11,512 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.4221: Install compressor air intakes in coolest locations | $2,611 | $100 |
$1,576
75,322
kWh
|
$1,035
-
kW-mo/yr
|
- | - | |
| 02 | 3.1191: Change procedures / equipment / operating conditions | $11,512 | - | - | - | - | $11,512 | |
| 03 | 3.1191: Change procedures / equipment / operating conditions | $5,309 | - | - | - | $5,309 | - | |
| TOTAL RECOMMENDED | $19,432 | $100 |
$1,576
75,322
kWh
|
$1,035
-
kW-mo/yr
|
$5,309 | $11,512 | ||
| TOTAL IMPLEMENTED | $11,512 | - | - | - | - | $11,512 | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs