ITAC Assessment: UL0237
ITAC logo
ITAC Assessment: UL0237
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1999
Principal Product Fabricated wire and metal parts
NAICS
n/a
SIC 3357: Drawing and Insulating of Nonferrous Wire
Sales Range $10
M
to 50
M
# of Employees 96
Plant Area 55,000
ft2
Annual Production 7,500,000
pieces
Production Hrs. Annual 6,336
hrs
Location (State) Kentucky

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $94,480 2,828,839
kWh
Electricity Demand $12,425 6,666
kW-mo/yr
Natural Gas $15,000 3,735
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $19,432 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $11,512

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Administrative Changes Savings Ancillary Material Cost Savings
01 2.4221: Install compressor air intakes in coolest locations $2,611 $100 $1,576
75,322
kWh
$1,035
-
kW-mo/yr
- -
02 3.1191: Change procedures / equipment / operating conditions $11,512 - - - - $11,512
03 3.1191: Change procedures / equipment / operating conditions $5,309 - - - $5,309 -
TOTAL RECOMMENDED $19,432 $100 $1,576
75,322
kWh
$1,035
-
kW-mo/yr
$5,309 $11,512
TOTAL IMPLEMENTED $11,512 - - - - $11,512
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs