Assessment Year | 1999 |
---|---|
Principal Product | Custon hardwood furniture pieces |
NAICS |
n/a
|
SIC | 2431: Millwork |
Sales Range | $10 M to 50M |
# of Employees | 162 |
Plant Area |
138,000
ft2
|
Annual Production | 3,500
thousand feet
|
Production Hrs. Annual | 6,452
hrs
|
Location (State) | Kentucky |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $84,081 | 3,362,544 |
kWh
|
$0.025 |
Electricity Demand | $106,450 | 10,797 |
kW-mo/yr
|
$9.86 |
Natural Gas | $35,131 | 8,127 |
MMBtu
|
$4.32 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $294,478 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $22,666 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Solid Waste (non-haz) Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.3212: Optimize plant power factor | $22,666 | $14,656 | - | - | $22,666 | - | - | |
02 | 2.4221: Install compressor air intakes in coolest locations | $742 | $65 |
$428
16,999
kWh
|
$314
-
kW-mo/yr
|
- | - | - | |
03 | 2.3412: Use waste heat to produce steam to drive a steam turbine-generator | $135,070 | $761,380 |
$78,416
2,862,837
kWh
|
$41,950
-
kW-mo/yr
|
- |
$14,704
-
lb
|
- | |
04 | 4.212: Adopt in-house material generation | $136,000 | $143,925 | - | - | - | - | $136,000 | |
TOTAL RECOMMENDED | $294,478 | $920,026 |
$78,844
2,879,836
kWh
|
$42,264
-
kW-mo/yr
|
$22,666 |
$14,704
-
lb
|
$136,000 | ||
TOTAL IMPLEMENTED | $22,666 | $14,656 | - | - | $22,666 | - | - |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs