ITAC Assessment: UL0223
ITAC logo
ITAC Assessment: UL0223
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1999
Principal Product Injection Molded Plastics
NAICS
n/a
SIC 3089: Plastics Products, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 120
Plant Area 60,000
ft2
Annual Production 70,000,000
lb
Production Hrs. Annual 6,732
hrs
Location (State) Indiana

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $146,473 4,024,619
kWh
Electricity Demand $35,923 10,276
kW-mo/yr
Natural Gas $6,052 922
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $726,637 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (non-haz) Savings Administrative Changes Savings One-time Revenue or Avoided Cost Savings
01 2.7111: Reduce illumination to minimum necessary levels $710 $101 $606
16,706
kWh
$104
-
kW-mo/yr
- - - -
02 2.7261: Install timers and/or thermostats $263 - - - $263
-
MMBtu
- - -
03 3.7198: Reduce / eliminate use of disposable product $844 $930 - - - $844
-
lb
- -
04 3.6193: Install equipment (eg compactor) to reduce disposal costs $3,000 $8,500 - - - - $3,000 -
05 4.515: Install shelves / racks to utilize unused space $721,820 $48,180 - - - - - $721,820
TOTAL RECOMMENDED $726,637 $57,711 $606
16,706
kWh
$104
-
kW-mo/yr
$263
-
MMBtu
$844
-
lb
$3,000 $721,820
TOTAL IMPLEMENTED - - - - - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs