| Assessment Year | 2008 |
|---|---|
| Principal Product | Resins and associated chemicals, coatings and slit rolls |
| NAICS | 325211: Plastics Material and Resin Manufacturing |
| SIC | 2821: Plastics Materials, Synthetic Resins, and Nonvulcanizable Elastomers |
| Sales Range | $10 M to 50M |
| # of Employees | 99 |
| Plant Area |
20,000
ft2
|
| Annual Production | 6,000,000
lb
|
| Production Hrs. Annual | 6,000
hrs
|
| Location (State) | Delaware |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $640,990 | 6,979,376 |
kWh
|
$0.092 |
| Electricity Demand | $86,778 | 1,191 |
kW-mo/yr
|
$72.86 |
| Natural Gas | $164,047 | 172,510 |
MMBtu
|
$0.95 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $23,264 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $10,013 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.4221: Install compressor air intakes in coolest locations | $1,841 | - |
$1,841
20,011
kWh
|
- | - | |
| 02 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $738 | - |
$665
7,223
kWh
|
$73
-
kW-mo/yr
|
- | |
| 03 | 2.4239: Eliminate or reduce compressed air usage | $1,007 | $800 |
$1,007
10,950
kWh
|
- | - | |
| 04 | 2.7293: Install dry sprinkler system or other method to reduce heating requirements | $6,100 | $12,100 |
$2,500
30,000
kWh
|
$3,600
-
kW-mo/yr
|
- | |
| 05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $9,006 | $26,496 |
$9,006
87,439
kWh
|
- | - | |
| 06 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $4,572 | $165,000 | - | - |
$4,572
-
MMBtu
|
|
| TOTAL RECOMMENDED | $23,264 | $204,396 |
$15,019
155,623
kWh
|
$3,673
-
kW-mo/yr
|
$4,572
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $10,013 | $27,296 |
$10,013
98,389
kWh
|
- | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs