ITAC Assessment: UL0212
ITAC logo
ITAC Assessment: UL0212
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1999
Principal Product Plastic refrigerator parts
NAICS
n/a
SIC 3089: Plastics Products, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 375
Plant Area 100,000
ft2
Annual Production 15,000,000
pieces
Production Hrs. Annual 8,760
hrs
Location (State) Kentucky

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $395,199 11,486,811
kWh
Electricity Demand $146,047 11,915
kW-mo/yr
Electricity Fees $71,080 -
Natural Gas $18,800 3,438
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $35,584 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Other Liquid (non-haz) Savings Solid Waste (non-haz) Savings By-product Production Savings
01 2.4221: Install compressor air intakes in coolest locations $1,802 $100 n/a $907
26,377
kWh
$895
-
kW-mo/yr
- - - -
02 2.3212: Optimize plant power factor $3,040 $2,176 n/a - - $3,040 - - -
03 3.7135: Minimize use of rags through worker training $3,175 $1,625 n/a - - - - $3,175
-
lb
-
04 3.6112: Use filter and drying oven to reduce sludge volume $1,567 $5,070 n/a - - - $1,567
-
gal
- -
05 4.514: Re-arrange equipment layout to reduce handling costs $26,000 $3,120 n/a - - - - - $26,000
TOTAL RECOMMENDED $35,584 $12,091 $907
26,377
kWh
$895
-
kW-mo/yr
$3,040 $1,567
-
gal
$3,175
-
lb
$26,000
TOTAL IMPLEMENTED - - - - - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs