ITAC Assessment: UL0203
ITAC logo
ITAC Assessment: UL0203
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1998
Principal Product Shelving from cold rolled steel
NAICS
n/a
SIC 3496: Miscellaneous Fabricated Wire Products
Sales Range $10
M
to 50
M
# of Employees 180
Plant Area 120,000
ft2
Annual Production 30,000,000
pieces
Production Hrs. Annual 6,000
hrs
Location (State) Indiana

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $118,408 4,605,803
kWh
Electricity Demand $78,241 9,528
kW-mo/yr
Electricity Fees $21,819 -
Natural Gas $109,509 33,874
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $229,577 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $20,777

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Solid Waste (non-haz) Savings Primary Product Savings
01 2.4221: Install compressor air intakes in coolest locations $2,115 $65 $2,115
50,410
kWh
- - -
02 2.2437: Recover waste heat from equipment $9,100 $20,100 - $9,100
-
MMBtu
- -
03 2.7111: Reduce illumination to minimum necessary levels $762 $15 $762
15,533
kWh
- - -
04 3.5315: Lease / purchase baler; sell cardboard to recycler $17,900 $8,860 - - $17,900
-
lb
-
05 3.1161: Eliminate/reduce an operation $109,700 $16,000 - - $109,700
-
lb
-
06 4.652: Replace existing equipment with more suitable substitutes $90,000 $155,600 - - - $90,000
TOTAL RECOMMENDED $229,577 $200,640 $2,877
65,943
kWh
$9,100
-
MMBtu
$127,600
-
lb
$90,000
TOTAL IMPLEMENTED $20,777 $8,940 $2,877
65,943
kWh
- $17,900
-
lb
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Solid Waste (non-haz) Savings Primary Product Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs