Assessment Year | 1998 |
---|---|
Principal Product | Reconstituted Leather Products |
NAICS |
n/a
|
SIC | 3111: Leather Tanning and Finishing |
Sales Range | $10 M to 50M |
# of Employees | 95 |
Plant Area |
130,000
ft2
|
Annual Production | 17,000,000
lb
|
Production Hrs. Annual | 5,664
hrs
|
Location (State) | Indiana |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $166,264 | 9,885,991 |
kWh
|
$0.017 |
Electricity Demand | $293,049 | 2,672 |
kW-mo/yr
|
$109.67 |
Natural Gas | $177,850 | 51,549 |
MMBtu
|
$3.45 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $189,642 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Water Disposal Savings | Solid Waste (non-haz) Savings | Primary Raw Material Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.8114: Change rate schedules or other changes in utility service | $4,000 | $7,000 | - | - | - | - | - | $4,000 | |
02 | 2.7261: Install timers and/or thermostats | $731 | $200 |
$731
43,376
kWh
|
- | - | - | - | - | |
03 | 2.4221: Install compressor air intakes in coolest locations | $971 | $131 |
$408
24,326
kWh
|
$563
-
kW-mo/yr
|
- | - | - | - | |
04 | 3.4112: Recovery metals from rinse water(evap., ion exchange, ro, electrolysis, electrodialysis) and reuse rinse water | $98,600 | $380,000 | - | - |
$98,600
-
Tgal
|
- | - | - | |
05 | 3.1163: Use plastic pallets instead of wood | $45,400 | $65,000 | - | - | - |
$45,400
-
lb
|
- | - | |
06 | 4.131: Modify process to reduce material use/cost | $39,940 | $70,000 | - | - | - | - | $39,940 | - | |
TOTAL RECOMMENDED | $189,642 | $522,331 |
$1,139
67,702
kWh
|
$563
-
kW-mo/yr
|
$98,600
-
Tgal
|
$45,400
-
lb
|
$39,940 | $4,000 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Water Disposal Savings | Solid Waste (non-haz) Savings | Primary Raw Material Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs