ITAC Assessment: UL0202
ITAC logo
ITAC Assessment: UL0202
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1998
Principal Product Reconstituted Leather Products
NAICS
n/a
SIC 3111: Leather Tanning and Finishing
Sales Range $10
M
to 50
M
# of Employees 95
Plant Area 130,000
ft2
Annual Production 17,000,000
lb
Production Hrs. Annual 5,664
hrs
Location (State) Indiana

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $166,264 9,885,991
kWh
Electricity Demand $293,049 2,672
kW-mo/yr
Natural Gas $177,850 51,549
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $189,642 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Water Disposal Savings Solid Waste (non-haz) Savings Primary Raw Material Savings Ancillary Material Cost Savings
01 2.8114: Change rate schedules or other changes in utility service $4,000 $7,000 - - - - - $4,000
02 2.7261: Install timers and/or thermostats $731 $200 $731
43,376
kWh
- - - - -
03 2.4221: Install compressor air intakes in coolest locations $971 $131 $408
24,326
kWh
$563
-
kW-mo/yr
- - - -
04 3.4112: Recovery metals from rinse water(evap., ion exchange, ro, electrolysis, electrodialysis) and reuse rinse water $98,600 $380,000 - - $98,600
-
Tgal
- - -
05 3.1163: Use plastic pallets instead of wood $45,400 $65,000 - - - $45,400
-
lb
- -
06 4.131: Modify process to reduce material use/cost $39,940 $70,000 - - - - $39,940 -
TOTAL RECOMMENDED $189,642 $522,331 $1,139
67,702
kWh
$563
-
kW-mo/yr
$98,600
-
Tgal
$45,400
-
lb
$39,940 $4,000
TOTAL IMPLEMENTED - - - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Water Disposal Savings Solid Waste (non-haz) Savings Primary Raw Material Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs