ITAC Assessment: UL0186
ITAC logo
ITAC Assessment: UL0186
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1997
Principal Product Stone washed denim clothing
NAICS
n/a
SIC 2263:
Sales Range $1
M
to 5
M
# of Employees 200
Plant Area 240,000
ft2
Annual Production 4,000,000
pieces
Production Hrs. Annual 8,736
hrs
Location (State) Indiana

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $101,189 1,913,247
kWh
Electricity Demand $89,619 8,527
kW-mo/yr
Natural Gas $336,243 97,072
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $1,941,665 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Solid Waste (non-haz) Savings Administrative Changes Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $362 $200 $204
3,810
kWh
$158
-
kW-mo/yr
- -
02 2.4133: Use most efficient type of electric motors $2,928 $20,490 $2,300
43,669
kWh
$628
-
kW-mo/yr
- -
03 2.4221: Install compressor air intakes in coolest locations $2,550 $30 $2,000
38,101
kWh
$550
-
kW-mo/yr
- -
04 3.4155: Meter waste water $53,265 $4,500 - - - $53,265
05 3.7212: Improved material handling (mixing and transfer) $2,560 $600 - - $2,560
-
lb
-
06 4.521: Clear and rent existing space $1,880,000 - - - - $1,880,000
TOTAL RECOMMENDED $1,941,665 $25,820 $4,504
85,580
kWh
$1,336
-
kW-mo/yr
$2,560
-
lb
$1,933,265
TOTAL IMPLEMENTED - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Solid Waste (non-haz) Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs