ITAC Assessment: UL0180
ITAC logo
ITAC Assessment: UL0180
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1997
Principal Product office furniture
NAICS
n/a
SIC 2521: Wood Office Furniture
Sales Range $10
M
to 50
M
# of Employees 160
Plant Area 162,576
ft2
Annual Production 9,000
pieces
Production Hrs. Annual 2,250
hrs
Location (State) Indiana

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $54,637 1,440,504
kWh
Electricity Demand $29,478 4,316
kW-mo/yr
Natural Gas $16,564 7,539
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $33,500 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $32,839

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Solid Waste (non-haz) Savings Solid Waste (haz) Savings Administrative Changes Savings
01 2.4133: Use most efficient type of electric motors $135 $3,650 $69
1,758
kWh
$66
-
kW-mo/yr
- - -
02 2.7142: Utilize higher efficiency lamps and/or ballasts $289 $2,813 $161
4,396
kWh
$128
-
kW-mo/yr
- - -
03 2.4221: Install compressor air intakes in coolest locations $526 $87 $266
7,034
kWh
$260
-
kW-mo/yr
- - -
04 3.1191: Change procedures / equipment / operating conditions $8,150 - - - - $8,150
-
lb
-
05 3.6193: Install equipment (eg compactor) to reduce disposal costs $5,000 $17,500 - - $5,000
-
lb
- -
06 4.431: Train operators for maximum operating efficiency $19,400 $3,600 - - - - $19,400
TOTAL RECOMMENDED $33,500 $27,650 $496
13,188
kWh
$454
-
kW-mo/yr
$5,000
-
lb
$8,150
-
lb
$19,400
TOTAL IMPLEMENTED $32,839 $23,913 $161
4,396
kWh
$128
-
kW-mo/yr
$5,000
-
lb
$8,150
-
lb
$19,400
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Solid Waste (non-haz) Savings Solid Waste (haz) Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs