Assessment Year | 1997 |
---|---|
Principal Product | Tenderized Wood Veneers |
NAICS |
n/a
|
SIC | 2435: Hardwood Veneer and Plywood |
Sales Range | $10 M to 50M |
# of Employees | 100 |
Plant Area |
60,000
ft2
|
Annual Production | 7,000
thousand feet
|
Production Hrs. Annual | 4,576
hrs
|
Location (State) | Kentucky |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $21,885 | 886,577 |
kWh
|
$0.025 |
Electricity Demand | $25,025 | 2,604 |
kW-mo/yr
|
$9.61 |
Natural Gas | $23,620 | 5,545 |
MMBtu
|
$4.26 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $870,377 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Other Liquid (haz) Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings | Primary Raw Material Savings |
---|---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.3212: Optimize plant power factor | $4,469 | $2,216 | - | - | - | - | - | - | $4,469 | - | |
02 | 2.7261: Install timers and/or thermostats | $429 | $400 | - | - |
$429
-
MMBtu
|
- | - | - | - | - | |
03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $249 | $20 |
$153
6,155
kWh
|
$96
-
kW-mo/yr
|
- | - | - | - | - | - | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $152 | $2,683 |
$80
3,224
kWh
|
$72
-
kW-mo/yr
|
- | - | - | - | - | - | |
05 | 3.6192: Use a less expensive method of waste removal | $6,082 | - | - | - | - | - | - |
$6,082
-
lb
|
- | - | |
06 | 3.4111: Use closed cycle process to minimize waste water production | $4,390 | $8,500 | - | - | - |
$4,390
-
Tgal
|
- | - | - | - | |
07 | 3.8141: Regenerate cleaning solvent on-site and reuse | $5,206 | $6,600 | - | - | - | - |
$5,206
-
gal
|
- | - | - | |
08 | 4.214: Purchase appropriately sized material | $569,400 | - | - | - | - | - | - | - | - | $569,400 | |
09 | 4.122: Develop standard procedures to improve internal yields | $280,000 | - | - | - | - | - | - | - | $280,000 | - | |
TOTAL RECOMMENDED | $870,377 | $20,419 |
$233
9,379
kWh
|
$168
-
kW-mo/yr
|
$429
-
MMBtu
|
$4,390
-
Tgal
|
$5,206
-
gal
|
$6,082
-
lb
|
$284,469 | $569,400 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Other Liquid (haz) Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings | Primary Raw Material Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs