ITAC Assessment: UL0179
ITAC logo
ITAC Assessment: UL0179
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1997
Principal Product Tenderized Wood Veneers
NAICS
n/a
SIC 2435: Hardwood Veneer and Plywood
Sales Range $10
M
to 50
M
# of Employees 100
Plant Area 60,000
ft2
Annual Production 7,000
thousand feet
Production Hrs. Annual 4,576
hrs
Location (State) Kentucky

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $21,885 886,577
kWh
Electricity Demand $25,025 2,604
kW-mo/yr
Natural Gas $23,620 5,545
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $870,377 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Other Liquid (haz) Savings Solid Waste (non-haz) Savings Administrative Changes Savings Primary Raw Material Savings
01 2.3212: Optimize plant power factor $4,469 $2,216 - - - - - - $4,469 -
02 2.7261: Install timers and/or thermostats $429 $400 - - $429
-
MMBtu
- - - - -
03 2.4231: Reduce the pressure of compressed air to the minimum required $249 $20 $153
6,155
kWh
$96
-
kW-mo/yr
- - - - - -
04 2.7142: Utilize higher efficiency lamps and/or ballasts $152 $2,683 $80
3,224
kWh
$72
-
kW-mo/yr
- - - - - -
05 3.6192: Use a less expensive method of waste removal $6,082 - - - - - - $6,082
-
lb
- -
06 3.4111: Use closed cycle process to minimize waste water production $4,390 $8,500 - - - $4,390
-
Tgal
- - - -
07 3.8141: Regenerate cleaning solvent on-site and reuse $5,206 $6,600 - - - - $5,206
-
gal
- - -
08 4.214: Purchase appropriately sized material $569,400 - - - - - - - - $569,400
09 4.122: Develop standard procedures to improve internal yields $280,000 - - - - - - - $280,000 -
TOTAL RECOMMENDED $870,377 $20,419 $233
9,379
kWh
$168
-
kW-mo/yr
$429
-
MMBtu
$4,390
-
Tgal
$5,206
-
gal
$6,082
-
lb
$284,469 $569,400
TOTAL IMPLEMENTED - - - - - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Other Liquid (haz) Savings Solid Waste (non-haz) Savings Administrative Changes Savings Primary Raw Material Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs