Assessment Year | 1998 |
---|---|
Principal Product | Plastic Moldings |
NAICS |
n/a
|
SIC | 3089: Plastics Products, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 106 |
Plant Area |
68,400
ft2
|
Annual Production | 16,000,000
pieces
|
Production Hrs. Annual | 7,488
hrs
|
Location (State) | Illinois |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $174,900 | 3,910,317 |
kWh
|
$0.045 |
Electricity Demand | $100,651 | 8,261 |
kW-mo/yr
|
$12.18 |
Electricity Fees | $3,160 | - |
|
- |
Natural Gas | $11,480 | 2,108 |
MMBtu
|
$5.45 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $34,419 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $18,439 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,658 | $3,870 |
$1,552
35,170
kWh
|
$685
-
kW-mo/yr
|
- | $421 | |
02 | 2.7135: Install occupancy sensors | $2,694 | $900 |
$1,891
42,790
kWh
|
$803
-
kW-mo/yr
|
- | - | |
03 | 2.2223: Enhance sensitivity of temperature control and cutoff | $2,600 | $450 | - | - |
$2,600
-
MMBtu
|
- | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,729 | $3,200 |
$967
29,894
kWh
|
$585
-
kW-mo/yr
|
- | $177 | |
05 | 2.4221: Install compressor air intakes in coolest locations | $920 | $200 |
$639
14,361
kWh
|
$281
-
kW-mo/yr
|
- | - | |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $686 | $850 |
$419
9,379
kWh
|
$267
-
kW-mo/yr
|
- | - | |
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $374 | $335 |
$162
3,810
kWh
|
$61
-
kW-mo/yr
|
- | $151 | |
08 | 3.5315: Lease / purchase baler; sell cardboard to recycler | $4,269 | $7,000 | - | - | - | $4,269 | |
09 | 3.5315: Lease / purchase baler; sell cardboard to recycler | $3,024 | $500 | - | - | - | $3,024 | |
10 | 4.122: Develop standard procedures to improve internal yields | $15,465 | $1,500 |
$4,298
97,011
kWh
|
$2,167
-
kW-mo/yr
|
- | $9,000 | |
TOTAL RECOMMENDED | $34,419 | $18,805 |
$9,928
232,415
kWh
|
$4,849
-
kW-mo/yr
|
$2,600
-
MMBtu
|
$17,042 | ||
TOTAL IMPLEMENTED | $18,439 | $2,285 |
$4,460
100,821
kWh
|
$2,228
-
kW-mo/yr
|
$2,600
-
MMBtu
|
$9,151 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs