Assessment Year | 1997 |
---|---|
Principal Product | Letterpress and Lithographic Printing |
NAICS |
n/a
|
SIC | 2759: Commercial Printing, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 180 |
Plant Area |
69,790
ft2
|
Annual Production | 0
pieces
|
Production Hrs. Annual | 7,776
hrs
|
Location (State) | Kentucky |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $97,459 | 3,606,682 |
kWh
|
$0.027 |
Electricity Demand | $73,434 | 7,638 |
kW-mo/yr
|
$9.61 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $422,588 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $802 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Other Liquid (non-haz) Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings | Primary Raw Material Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $802 | $1,661 |
$444
16,413
kWh
|
$358
-
kW-mo/yr
|
- | - | - | - | - | |
02 | 2.4133: Use most efficient type of electric motors | $136 | $3,180 |
$88
3,224
kWh
|
$48
-
kW-mo/yr
|
- | - | - | - | - | |
03 | 3.5121: Recycle waste ink and cleanup solvent | $45,321 | - | - | - |
$3,640
-
gal
|
- | - | $41,681 | - | |
04 | 4.231: Purchase equipment instead of leasing | $11,180 | $4,500 | - | - | - | - | $11,180 | - | - | |
05 | 4.211: Consider use / purchase of bulk materials where possible | $9,373 | $400 | - | - | - |
$373
-
lb
|
- | $9,000 | - | |
06 | 4.514: Re-arrange equipment layout to reduce handling costs | $355,776 | $77,600 | - | - | - | - | - | - | $355,776 | |
TOTAL RECOMMENDED | $422,588 | $87,341 |
$532
19,637
kWh
|
$406
-
kW-mo/yr
|
$3,640
-
gal
|
$373
-
lb
|
$11,180 | $50,681 | $355,776 | ||
TOTAL IMPLEMENTED | $802 | $1,661 |
$444
16,413
kWh
|
$358
-
kW-mo/yr
|
- | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Other Liquid (non-haz) Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings | Primary Raw Material Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs