Assessment Year | 1996 |
---|---|
Principal Product | Offset Printing |
NAICS |
n/a
|
SIC | 2752: Commercial Printing, Lithographic |
Sales Range | $10 M to 50M |
# of Employees | 120 |
Plant Area |
70,000
ft2
|
Annual Production | 900,000
lb
|
Production Hrs. Annual | 8,400
hrs
|
Location (State) | Kentucky |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $61,574 | 1,170,574 |
kWh
|
$0.053 |
Electricity Demand | $31,988 | 3,345 |
kW-mo/yr
|
$9.56 |
Natural Gas | $2,021 | 517 |
MMBtu
|
$3.91 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $14,406 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $6,742 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings | Primary Raw Material Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.3212: Optimize plant power factor | $6,640 | $3,694 | - |
$6,640
-
kW-mo/yr
|
- | - | - | - | |
02 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,562 | $20 |
$1,094
38,687
kWh
|
$468
-
kW-mo/yr
|
- | - | - | - | |
03 | 2.7261: Install timers and/or thermostats | $102 | $200 | - | - |
$102
-
MMBtu
|
- | - | - | |
04 | 3.6192: Use a less expensive method of waste removal | $2,300 | - | - | - | - | - | $2,300 | - | |
05 | 4.211: Consider use / purchase of bulk materials where possible | $3,802 | $500 | - | - | - |
$52
-
lb
|
- | $3,750 | |
TOTAL RECOMMENDED | $14,406 | $4,414 |
$1,094
38,687
kWh
|
$7,108
-
kW-mo/yr
|
$102
-
MMBtu
|
$52
-
lb
|
$2,300 | $3,750 | ||
TOTAL IMPLEMENTED | $6,742 | $3,894 | - |
$6,640
-
kW-mo/yr
|
$102
-
MMBtu
|
- | - | - |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs