ITAC Assessment: UL0169
ITAC logo
ITAC Assessment: UL0169
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1996
Principal Product Offset Printing
NAICS
n/a
SIC 2752: Commercial Printing, Lithographic
Sales Range $10
M
to 50
M
# of Employees 120
Plant Area 70,000
ft2
Annual Production 900,000
lb
Production Hrs. Annual 8,400
hrs
Location (State) Kentucky

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $61,574 1,170,574
kWh
Electricity Demand $31,988 3,345
kW-mo/yr
Natural Gas $2,021 517
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $14,406 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $6,742

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (non-haz) Savings Administrative Changes Savings Primary Raw Material Savings
01 2.3212: Optimize plant power factor $6,640 $3,694 - $6,640
-
kW-mo/yr
- - - -
02 2.4231: Reduce the pressure of compressed air to the minimum required $1,562 $20 $1,094
38,687
kWh
$468
-
kW-mo/yr
- - - -
03 2.7261: Install timers and/or thermostats $102 $200 - - $102
-
MMBtu
- - -
04 3.6192: Use a less expensive method of waste removal $2,300 - - - - - $2,300 -
05 4.211: Consider use / purchase of bulk materials where possible $3,802 $500 - - - $52
-
lb
- $3,750
TOTAL RECOMMENDED $14,406 $4,414 $1,094
38,687
kWh
$7,108
-
kW-mo/yr
$102
-
MMBtu
$52
-
lb
$2,300 $3,750
TOTAL IMPLEMENTED $6,742 $3,894 - $6,640
-
kW-mo/yr
$102
-
MMBtu
- - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs