ITAC Assessment: UL0122
ITAC logo
ITAC Assessment: UL0122
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1995
Principal Product Sealing Devices, Piston Rings
NAICS
n/a
SIC 3592: Carburetors, Pistons, Piston Rings, and Valves
Sales Range $10
M
to 50
M
# of Employees 250
Plant Area 163,350
ft2
Annual Production 187,000
pieces
Production Hrs. Annual 4,500
hrs
Location (State) Kentucky

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $183,841 3,063,306
kWh
Natural Gas $64,323 15,148
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $16,031 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $5,493 $2,529 $5,493
91,442
kWh
-
02 2.4133: Use most efficient type of electric motors $4,310 $7,520 $4,310
71,805
kWh
-
03 2.4111: Utilize energy-efficient belts and other improved mechanisms $3,488 $5,143 $3,488
58,030
kWh
-
04 2.4221: Install compressor air intakes in coolest locations $769 $10 $769
12,896
kWh
-
05 2.1233: Analyze flue gas for proper air/fuel ratio $569 $1,000 - $569
-
MMBtu
06 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,402 $40 $1,402
23,154
kWh
-
TOTAL RECOMMENDED $16,031 $16,242 $15,462
257,327
kWh
$569
-
MMBtu
TOTAL IMPLEMENTED - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs