ITAC Assessment: UL0118
ITAC logo
ITAC Assessment: UL0118
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1995
Principal Product Stone washed blue jeans
NAICS
n/a
SIC 2263:
Sales Range $1
M
to 5
M
# of Employees 125
Plant Area 87,000
ft2
Annual Production 3,750,000
pieces
Production Hrs. Annual 8,400
hrs
Location (State) Indiana

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $95,282 1,718,640
kWh
Natural Gas $268,293 61,243
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $114,165 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Water Disposal Savings Solid Waste (non-haz) Savings
01 2.1233: Analyze flue gas for proper air/fuel ratio $20,589 $2,000 - $20,589
-
MMBtu
- -
02 2.4221: Install compressor air intakes in coolest locations $586 $10 $586
10,551
kWh
- - -
03 2.4133: Use most efficient type of electric motors $5,551 $4,400 $5,551
100,234
kWh
- - -
04 2.7142: Utilize higher efficiency lamps and/or ballasts $1,879 $1,583 $1,879
38,394
kWh
- - -
05 2.3212: Optimize plant power factor $24,960 $12,260 $24,960
-
kWh
- - -
06 3.4155: Meter waste water $24,300 $1,000 - - $24,300
-
Tgal
-
07 3.4113: Treat and reuse rinse waters $33,500 $10,500 - - $33,500
-
Tgal
-
08 3.6192: Use a less expensive method of waste removal $2,800 $5,000 - - - $2,800
-
lb
TOTAL RECOMMENDED $114,165 $36,753 $32,976
149,179
kWh
$20,589
-
MMBtu
$57,800
-
Tgal
$2,800
-
lb
TOTAL IMPLEMENTED - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Water Disposal Savings Solid Waste (non-haz) Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs