ITAC Assessment: UD0916
ITAC logo
ITAC Assessment: UD0916
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2014
Principal Product Copper and Bronze Casting
NAICS 331529: Other Nonferrous Metal Foundries (except Die-Casting)
SIC 3366: Copper Foundries
Sales Range $10
M
to 50
M
# of Employees 92
Plant Area 175,000
ft2
Annual Production 6,000,000
lb
Production Hrs. Annual 4,992
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $221,313 4,114,826
kWh
Electricity Demand $89,608 26,832
kW-mo/yr
Natural Gas $137,912 21,908
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $95,963 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $30,843

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Personnel Changes Savings Ancillary Material Cost Savings
01 2.6218: Turn off equipment when not in use $5,270 - $5,270
115,212
kWh
- - - - -
02 2.4111: Utilize energy-efficient belts and other improved mechanisms $2,027 - $1,728
37,283
kWh
$299
-
kW-mo/yr
- - - -
03 2.4113: Install motor voltage controller on lightly loaded motors $6,076 $11,700 $5,179
111,721
kWh
$897
-
kW-mo/yr
- - - -
04 2.2449: Recover heat from exhausted steam, hot air or hot water $25,351 $43,280 - - - $25,351
-
MMBtu
- -
05 2.7142: Utilize higher efficiency lamps and/or ballasts $14,413 $26,040 $9,701
209,233
kWh
$1,680
-
kW-mo/yr
$3,032 - - -
06 2.7135: Install occupancy sensors $503 $500 $347
7,479
kWh
$60
-
kW-mo/yr
$96 - - -
07 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $1,426 $4,150 $1,426
30,750
kWh
- - - - -
08 2.4231: Reduce the pressure of compressed air to the minimum required $896 - $764
16,474
kWh
$132
-
kW-mo/yr
- - - -
09 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $6,978 $1,000 $6,200
134,229
kWh
$1,078
-
kW-mo/yr
- - $(-300.0) -
10 2.4224: Upgrade controls on compressors $10,562 $110,000 $9,003
194,189
kWh
$1,559
-
kW-mo/yr
- - - -
11 2.2223: Enhance sensitivity of temperature control and cutoff $9,661 $40,000 - - - $9,661
-
MMBtu
- -
12 3.5316: Contract a wood pallet recycling company $12,800 - - - - - - $12,800
TOTAL RECOMMENDED $95,963 $236,670 $39,618
856,570
kWh
$5,705
-
kW-mo/yr
$3,128 $35,012
-
MMBtu
$(-300.0) $12,800
TOTAL IMPLEMENTED $30,843 $111,500 $15,550
335,897
kWh
$2,697
-
kW-mo/yr
$96 - $(-300.0) $12,800
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Personnel Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs