Assessment Year | 1995 |
---|---|
Principal Product | Denim Blue Jeans |
NAICS |
n/a
|
SIC | 2263: |
Sales Range | $5 M to 10M |
# of Employees | 10 |
Plant Area |
25,000
ft2
|
Annual Production | 10,000,000
pieces
|
Production Hrs. Annual | 8,064
hrs
|
Location (State) | Kentucky |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $208,865 | 4,072,978 |
kWh
|
$0.051 |
Natural Gas | $15,750 | 3,559 |
MMBtu
|
$4.43 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $95,582 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Water Disposal Savings | Solid Waste (non-haz) Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.4221: Install compressor air intakes in coolest locations | $149 | $25 |
$149
2,931
kWh
|
- | - | - | |
02 | 2.4133: Use most efficient type of electric motors | $4,441 | $22,850 |
$4,441
86,460
kWh
|
- | - | - | |
03 | 2.3212: Optimize plant power factor | $1,046 | $808 |
$1,046
-
kWh
|
- | - | - | |
04 | 2.1131: Repair faulty insulation in furnaces, boilers, etc | $1,593 | $1,146 | - |
$1,593
-
MMBtu
|
- | - | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,993 | $2,077 |
$1,993
38,980
kWh
|
- | - | - | |
06 | 3.4155: Meter waste water | $8,000 | $1,000 | - | - |
$8,000
-
Tgal
|
- | |
07 | 3.4113: Treat and reuse rinse waters | $70,000 | $8,000 | - | - |
$70,000
-
Tgal
|
- | |
08 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $3,100 | $5,000 | - | - | - |
$3,100
-
lb
|
|
09 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $1,660 | $1,000 | - | - |
$1,660
-
Tgal
|
- | |
10 | 3.6113: Remove sludge from tanks on a regular basis | $3,600 | $5,000 | - | - |
$3,600
-
Tgal
|
- | |
TOTAL RECOMMENDED | $95,582 | $46,906 |
$7,629
128,371
kWh
|
$1,593
-
MMBtu
|
$83,260
-
Tgal
|
$3,100
-
lb
|
||
TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Water Disposal Savings | Solid Waste (non-haz) Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs