| Assessment Year | 1994 |
|---|---|
| Principal Product | Asphalt Shingles |
| NAICS |
n/a
|
| SIC | 2952: Asphalt Felts and Coatings |
| Sales Range | $50 M to 100M |
| # of Employees | 154 |
| Plant Area |
126,000
ft2
|
| Annual Production | 4,500,000
pieces
|
| Production Hrs. Annual | 6,432
hrs
|
| Location (State) | Indiana |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $483,800 | 11,427,316 |
kWh
|
$0.042 |
| Fuel Oil #2 | $585,387 | 206,074 |
MMBtu
|
$2.84 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $27,562 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $13,590 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Fuel Oil #2 Savings |
|---|---|---|---|---|---|---|
| 01 | 2.3212: Optimize plant power factor | $9,114 | $19,020 |
$9,114
-
kWh
|
- | |
| 02 | 2.1213: Direct warmest air to combustion intake | $13,700 | $7,500 | - |
$13,700
-
MMBtu
|
|
| 03 | 2.4133: Use most efficient type of electric motors | $4,024 | $9,700 |
$4,024
200,762
kWh
|
- | |
| 04 | 2.4221: Install compressor air intakes in coolest locations | $452 | $350 |
$452
10,844
kWh
|
- | |
| 05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $272 | $745 |
$272
6,448
kWh
|
- | |
| TOTAL RECOMMENDED | $27,562 | $37,315 |
$13,862
218,054
kWh
|
$13,700
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $13,590 | $29,070 |
$13,590
211,606
kWh
|
- | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs