| Assessment Year | 2013 |
|---|---|
| Principal Product | Lumber |
| NAICS | 321912: Cut Stock, Resawing Lumber, and Planing |
| SIC | 2421: Sawmills and Planing Mills, General |
| Sales Range | $10 M to 50M |
| # of Employees | 129 |
| Plant Area |
3,852,980
ft2
|
| Annual Production | 95,000,000
thousand feet
|
| Production Hrs. Annual | 8,568
hrs
|
| Location (State) | Idaho |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $472,037 | 15,787,200 |
kWh
|
$0.030 |
| Electricity Demand | $207,050 | 34,508 |
kW-mo/yr
|
$6.00 |
| Wood | $176,699 | 339,261 |
MMBtu
|
$0.52 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $491,849 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Wood Savings | Water Consumption Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.2127: Flash condensate to produce lower pressure steam | $209,585 | $54,045 | - |
$18,677
-
MMBtu
|
$190,908
-
Tgal
|
|
| 02 | 2.6212: Turn off equipment during breaks, reduce operating time | $11,574 | $752 |
$11,574
385,780
kWh
|
- | - | |
| 03 | 2.2511: Insulate bare equipment | $258 | $1,952 | - |
$258
-
MMBtu
|
- | |
| 04 | 2.7135: Install occupancy sensors | $311 | $240 |
$311
10,364
kWh
|
- | - | |
| 05 | 2.2113: Repair or replace steam traps | $264,262 | $84,783 | - |
$23,550
-
MMBtu
|
$240,712
-
Tgal
|
|
| 06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $441 | $973 |
$441
14,698
kWh
|
- | - | |
| 07 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $5,418 | $16,300 |
$5,418
180,593
kWh
|
- | - | |
| TOTAL RECOMMENDED | $491,849 | $159,045 |
$17,744
591,435
kWh
|
$42,485
-
MMBtu
|
$431,620
-
Tgal
|
||
| TOTAL IMPLEMENTED | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Wood Savings | Water Consumption Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs