Assessment Year | 2013 |
---|---|
Principal Product | Lumber |
NAICS | 321912: Cut Stock, Resawing Lumber, and Planing |
SIC | 2421: Sawmills and Planing Mills, General |
Sales Range | $10 M to 50M |
# of Employees | 129 |
Plant Area |
3,852,980
ft2
|
Annual Production | 95,000,000
thousand feet
|
Production Hrs. Annual | 8,568
hrs
|
Location (State) | Idaho |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $472,037 | 15,787,200 |
kWh
|
$0.030 |
Electricity Demand | $207,050 | 34,508 |
kW-mo/yr
|
$6.00 |
Wood | $176,699 | 339,261 |
MMBtu
|
$0.52 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $491,849 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Wood Savings | Water Consumption Savings |
---|---|---|---|---|---|---|---|
01 | 2.2127: Flash condensate to produce lower pressure steam | $209,585 | $54,045 | - |
$18,677
-
MMBtu
|
$190,908
-
Tgal
|
|
02 | 2.6212: Turn off equipment during breaks, reduce operating time | $11,574 | $752 |
$11,574
385,780
kWh
|
- | - | |
03 | 2.2511: Insulate bare equipment | $258 | $1,952 | - |
$258
-
MMBtu
|
- | |
04 | 2.7135: Install occupancy sensors | $311 | $240 |
$311
10,364
kWh
|
- | - | |
05 | 2.2113: Repair or replace steam traps | $264,262 | $84,783 | - |
$23,550
-
MMBtu
|
$240,712
-
Tgal
|
|
06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $441 | $973 |
$441
14,698
kWh
|
- | - | |
07 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $5,418 | $16,300 |
$5,418
180,593
kWh
|
- | - | |
TOTAL RECOMMENDED | $491,849 | $159,045 |
$17,744
591,435
kWh
|
$42,485
-
MMBtu
|
$431,620
-
Tgal
|
||
TOTAL IMPLEMENTED | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Wood Savings | Water Consumption Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs