ITAC Assessment: UK1908
ITAC logo
ITAC Assessment: UK1908
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2019
Principal Product Steel Automotive Wheels
NAICS 336330: Motor Vehicle Steering and Suspension Components (except Spring) Manufacturing
SIC 3714: Motor Vehicle Parts and Accessories
Sales Range $50
M
to 100
M
# of Employees 193
Plant Area 402,110
ft2
Annual Production 4,381,556
units
Production Hrs. Annual 4,500
hrs
Location (State) Kentucky

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $803,091 25,110,567
kWh
Electricity Demand $1,076,603 65,659
kW-mo/yr
Electricity Fees $21,658 -
Natural Gas $314,344 66,889
MMBtu
Waste Disposal Costs
Water Usage $457,338 120,853
Tgal
TOTAL YEARLY COSTS $2,673,034
RECOMMENDED SAVINGS* $345,487 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $288,087

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.4231: Reduce the pressure of compressed air to the minimum required $24,319 - $12,511
390,966
kWh
$11,808
-
kW-mo/yr
-
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $40,190 $3,038 $23,659
739,344
kWh
$16,531
-
kW-mo/yr
-
03 2.4226: Use / purchase optimum sized compressor $116,074 $438,000 $37,157
1,161,164
kWh
$78,917
-
kW-mo/yr
-
04 2.7224: Reduce space conditioning during non-working hours $553 $227 $553
17,226
kWh
- -
05 2.7142: Utilize higher efficiency lamps and/or ballasts $10,676 $22,903 $4,296
134,259
kWh
$6,380
-
kW-mo/yr
-
06 2.7124: Make a practice of turning off lights when not needed $1,551 - $1,551
48,482
kWh
- -
07 2.7122: Disconnect ballasts $383 $72 $226
7,061
kWh
$157
-
kW-mo/yr
-
08 2.4111: Utilize energy-efficient belts and other improved mechanisms $914 $720 $386
12,060
kWh
$528
-
kW-mo/yr
-
09 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $4,838 $1,900 $2,050
64,065
kWh
$2,788
-
kW-mo/yr
-
10 2.5123: Reduce fluid flow rates $2,913 $1,900 $1,732
54,110
kWh
$1,181
-
kW-mo/yr
-
11 2.2691: Shut off cooling if cold outside air will cool process $13,831 $5,000 $13,831
432,216
kWh
- -
12 2.2615: Clean condenser tubes $15,832 $7,858 $9,338
291,813
kWh
$6,494
-
kW-mo/yr
-
13 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $9,547 $8,300 $5,857
183,032
kWh
$3,690
-
kW-mo/yr
-
14 2.2531: Re-size charging openings or add movable cover or door $3,671 $2,684 $3,671
114,732
kWh
- -
15 2.1122: Re-size charging openings or add a movable door on equipment $63,247 $2,368 $16,684
521,361
kWh
- $46,563
-
MMBtu
16 2.2511: Insulate bare equipment $13,639 $18,226 - - $13,639
-
MMBtu
17 2.2312: Minimize non-essential material in heat treatment process $1,430 - $382
11,937
kWh
- $1,048
-
MMBtu
18 2.2711: Utilize outside air instead of conditioned air for drying $21,879 $28,230 $21,879
683,728
kWh
- -
TOTAL RECOMMENDED $345,487 $541,426 $155,763
4,867,556
kWh
$128,474
-
kW-mo/yr
$61,250
-
MMBtu
TOTAL IMPLEMENTED $288,087 $484,439 $113,711
3,553,484
kWh
$126,765
-
kW-mo/yr
$47,611
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs