ITAC Assessment: UK1810
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2018
Principal Product Wastewater Treatment
NAICS 221320: Sewage Treatment Facilities
SIC 4952: Sewerage Systems
Sales Range $5
M
to 10
M
# of Employees 30
Plant Area 27,500
ft2
Annual Production 5,000
Tgal
Production Hrs. Annual 8,760
hrs
Location (State) Kentucky

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $413,294 5,519,400
kWh
Electricity Demand $83,047 9,096
kW-mo/yr
Electricity Fees $109,650 -
Waste Disposal Costs
Water Usage $90,129 468,322
Tgal
TOTAL YEARLY COSTS $696,120
RECOMMENDED SAVINGS* $90,230 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $69,201

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Water Usage Savings One-time Revenue or Avoided Cost Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $7,656 $10,541 $6,078
81,035
kWh
$1,578
-
kW-mo/yr
- -
02 3.1161: Eliminate/reduce an operation $21,029 $10,000 $21,029
280,390
kWh
- - -
03 2.4152: Use only certified motor repair shops $902 $2,215 $833
11,108
kWh
- - $69
04 3.1191: Change procedures / equipment / operating conditions $36,700 $5,900 $36,700
489,333
kWh
- - -
05 2.7224: Reduce space conditioning during non-working hours $1,415 - $1,210
16,128
kWh
$205
-
kW-mo/yr
- -
06 3.4159: Replace treated water with well / surface water $22,528 $8,200 $(-36,759.0)
(-490,122)
kWh
- $59,287
-
Tgal
-
TOTAL RECOMMENDED $90,230 $36,856 $29,091
387,872
kWh
$1,783
-
kW-mo/yr
$59,287
-
Tgal
$69
TOTAL IMPLEMENTED $69,201 $26,856 $8,062
107,482
kWh
$1,783
-
kW-mo/yr
$59,287
-
Tgal
$69
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Water Usage Savings One-time Revenue or Avoided Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs