Assessment Year | 2018 |
---|---|
Principal Product | Wastewater Treatment |
NAICS | 221320: Sewage Treatment Facilities |
SIC | 4952: Sewerage Systems |
Sales Range | $10 M to 50M |
# of Employees | 78 |
Plant Area |
16,600
ft2
|
Annual Production | 2,920,000,000
Tgal
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Kentucky |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $530,902 | 7,165,800 |
kWh
|
$0.074 |
Electricity Demand | $131,160 | 14,366 |
kW-mo/yr
|
$9.13 |
Electricity Fees | $135,684 | - |
|
- |
Natural Gas | $3,475 | 421 |
MMBtu
|
$8.25 |
TOTAL YEARLY COSTS | $801,221 | |||
RECOMMENDED SAVINGS* | $318,703 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $28,551 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.7224: Reduce space conditioning during non-working hours | $106 | - |
$106
1,426
kWh
|
- | - | - | |
02 | 2.7145: Install skylights | $126 | $40 |
$126
1,708
kWh
|
- | - | - | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $14,341 | $12,798 |
$11,197
151,317
kWh
|
$3,144
-
kW-mo/yr
|
- | - | |
04 | 2.7135: Install occupancy sensors | $1,191 | $690 |
$1,191
16,103
kWh
|
- | - | - | |
05 | 2.4152: Use only certified motor repair shops | $2,941 | $378 |
$2,505
33,849
kWh
|
$427
-
kW-mo/yr
|
- | $9 | |
06 | 2.6212: Turn off equipment during breaks, reduce operating time | $290,152 | $2,325 |
$290,152
3,920,976
kWh
|
- | - | - | |
07 | 2.6218: Turn off equipment when not in use | $2,101 | $500 |
$887
11,981
kWh
|
- |
$1,214
-
MMBtu
|
- | |
08 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $213 | $12 |
$182
2,453
kWh
|
$31
-
kW-mo/yr
|
- | - | |
09 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $7,532 | $3,400 |
$6,448
87,133
kWh
|
$1,084
-
kW-mo/yr
|
- | - | |
TOTAL RECOMMENDED | $318,703 | $20,143 |
$312,794
4,226,946
kWh
|
$4,686
-
kW-mo/yr
|
$1,214
-
MMBtu
|
$9 | ||
TOTAL IMPLEMENTED | $28,551 | $17,818 |
$22,642
305,970
kWh
|
$4,686
-
kW-mo/yr
|
$1,214
-
MMBtu
|
$9 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | One-time Revenue or Avoided Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs