Assessment Year | 2017 |
---|---|
Principal Product | Powertrain Fasteners |
NAICS | 339993: Fastener, Button, Needle, and Pin Manufacturing |
SIC | 3965: Fasteners, Buttons, Needles, and Pins |
Sales Range | $10 M to 50M |
# of Employees | 116 |
Plant Area |
100,000
ft2
|
Annual Production | 1,000,000
pieces
|
Production Hrs. Annual | 7,200
hrs
|
Location (State) | Kentucky |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $136,854 | 3,998,880 |
kWh
|
$0.034 |
Electricity Demand | $137,318 | 7,816 |
kW-mo/yr
|
$17.57 |
Electricity Fees | $6,282 | - |
|
- |
Natural Gas | $14,698 | 1,884 |
MMBtu
|
$7.80 |
TOTAL YEARLY COSTS | $295,152 | |||
RECOMMENDED SAVINGS* | $29,686 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $6,732 | $2,100 |
$6,732
198,000
kWh
|
- | - | |
02 | 2.4238: Do not use compressed air for personal cooling | $1,143 | - |
$1,143
33,627
kWh
|
- | - | |
03 | 2.4239: Eliminate or reduce compressed air usage | $1,114 | $453 |
$1,114
32,760
kWh
|
- | - | |
04 | 2.6212: Turn off equipment during breaks, reduce operating time | $338 | - |
$338
9,943
kWh
|
- | - | |
05 | 2.2442: Preheat combustion air with waste heat | $5,407 | $3,304 | - | - |
$5,407
-
MMBtu
|
|
06 | 2.7224: Reduce space conditioning during non-working hours | $3,910 | - |
$2,600
76,464
kWh
|
- |
$1,310
-
MMBtu
|
|
07 | 2.7224: Reduce space conditioning during non-working hours | $2,536 | - |
$1,444
42,480
kWh
|
- |
$1,092
-
MMBtu
|
|
08 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $1,908 | - |
$1,028
30,240
kWh
|
$880
-
kW-mo/yr
|
- | |
09 | 2.4152: Use only certified motor repair shops | $1,400 | $2,734 |
$749
22,034
kWh
|
$651
-
kW-mo/yr
|
- | |
10 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,596 | $2,983 |
$857
25,201
kWh
|
$739
-
kW-mo/yr
|
- | |
11 | 2.7144: Install spectral reflectors / delamp | $1,368 | $113 |
$734
21,600
kWh
|
$634
-
kW-mo/yr
|
- | |
12 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,293 | $1,481 |
$536
15,760
kWh
|
$757
-
kW-mo/yr
|
- | |
13 | 2.7111: Reduce illumination to minimum necessary levels | $941 | $1,492 |
$501
14,746
kWh
|
$440
-
kW-mo/yr
|
- | |
TOTAL RECOMMENDED | $29,686 | $14,660 |
$17,776
522,855
kWh
|
$4,101
-
kW-mo/yr
|
$7,809
-
MMBtu
|
||
TOTAL IMPLEMENTED | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs