Assessment Year | 2017 |
---|---|
Principal Product | Wood and Vinyl Windows and Doors |
NAICS | 321911: Wood Window and Door Manufacturing |
SIC | 2431: Millwork |
Sales Range | $10 M to 50M |
# of Employees | 120 |
Plant Area |
250,000
ft2
|
Annual Production | 30,000
units
|
Production Hrs. Annual | 2,080
hrs
|
Location (State) | Kentucky |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $148,879 | 1,316,320 |
kWh
|
$0.11 |
Electricity Demand | $31,182 | 7,069 |
kW-mo/yr
|
$4.41 |
Electricity Fees | $262 | - |
|
- |
Natural Gas | $43,559 | 7,194 |
MMBtu
|
$6.05 |
TOTAL YEARLY COSTS | $223,882 | |||
RECOMMENDED SAVINGS* | $58,226 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $18,979 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.1135: Repair furnaces and oven doors so that they seal efficiently | $137 | $100 | - | - |
$137
-
MMBtu
|
- | - | |
02 | 2.1135: Repair furnaces and oven doors so that they seal efficiently | $7,994 | $2,000 | - | - |
$7,994
-
MMBtu
|
- | - | |
03 | 2.6218: Turn off equipment when not in use | $4,191 | - | - | - |
$4,191
-
MMBtu
|
- | - | |
04 | 2.6218: Turn off equipment when not in use | $1,753 | $1,000 |
$1,753
15,517
kWh
|
- | - | - | - | |
05 | 2.2211: Use optimum temperature | $344 | - |
$265
2,347
kWh
|
$79
-
kW-mo/yr
|
- | - | - | |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,444 | $2,232 |
$1,346
11,914
kWh
|
- | - | - | $98 | |
07 | 2.7134: Use photocell controls | $475 | $512 |
$475
4,203
kWh
|
- | - | - | - | |
08 | 2.7135: Install occupancy sensors | $1,017 | $618 |
$1,017
8,997
kWh
|
- | - | - | - | |
09 | 2.7135: Install occupancy sensors | $1,123 | $338 |
$1,123
9,942
kWh
|
- | - | - | - | |
10 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,938 | $2,268 |
$2,938
26,000
kWh
|
- | - | - | - | |
11 | 2.4231: Reduce the pressure of compressed air to the minimum required | $780 | - |
$780
6,907
kWh
|
- | - | - | - | |
12 | 2.6218: Turn off equipment when not in use | $742 | - |
$742
6,569
kWh
|
- | - | - | - | |
13 | 2.4221: Install compressor air intakes in coolest locations | $604 | $382 |
$604
5,341
kWh
|
- | - | - | - | |
14 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $576 | - |
$470
4,160
kWh
|
$106
-
kW-mo/yr
|
- | - | - | |
15 | 2.6212: Turn off equipment during breaks, reduce operating time | $34,108 | $20,000 |
$4,936
43,680
kWh
|
$476
-
kW-mo/yr
|
- | $28,696 | - | |
TOTAL RECOMMENDED | $58,226 | $29,450 |
$16,449
145,577
kWh
|
$661
-
kW-mo/yr
|
$12,322
-
MMBtu
|
$28,696 | $98 | ||
TOTAL IMPLEMENTED | $18,979 | $9,068 |
$10,644
94,209
kWh
|
$106
-
kW-mo/yr
|
$8,131
-
MMBtu
|
- | $98 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs