| Assessment Year | 2017 |
|---|---|
| Principal Product | Trailer Suspension Systems |
| NAICS | 336330: Motor Vehicle Steering and Suspension Components (except Spring) Manufacturing |
| SIC | 3537: Industrial Trucks, Tractors, Trailers, and Stackers |
| Sales Range | $10 M to 50M |
| # of Employees | 330 |
| Plant Area |
105,000
ft2
|
| Annual Production | 1,000,000
units
|
| Production Hrs. Annual | 3,640
hrs
|
| Location (State) | Kentucky |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $207,317 | 2,752,600 |
kWh
|
$0.075 | |
| Electricity Demand | $45,091 | 5,900 |
kW-mo/yr
|
$7.64 | |
| Electricity Fees | $1,310 | - |
|
- | |
| Natural Gas | $93,967 | 8,595 |
MMBtu
|
$10.93 | |
| Waste Disposal Costs | |||||
| Water Usage | $19,830 | 2,885 |
Tgal
|
$6.87 | |
| Water Disposal | $12,931 | 2,885 |
Tgal
|
$4.48 | |
| TOTAL YEARLY COSTS | $380,446 | ||||
| RECOMMENDED SAVINGS* | $55,567 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | - | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.4239: Eliminate or reduce compressed air usage | $22,720 | $38,000 |
$15,374
204,173
kWh
|
$7,346
-
kW-mo/yr
|
- | - | |
| 02 | 2.4231: Reduce the pressure of compressed air to the minimum required | $2,900 | - |
$2,900
38,518
kWh
|
- | - | - | |
| 03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,934 | $3,000 |
$1,934
25,679
kWh
|
- | - | - | |
| 04 | 2.7145: Install skylights | $9,639 | $11,580 |
$9,639
128,007
kWh
|
- | - | - | |
| 05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,475 | $3,350 |
$1,154
15,330
kWh
|
$321
-
kW-mo/yr
|
- | - | |
| 06 | 2.7124: Make a practice of turning off lights when not needed | $841 | $72 |
$630
8,372
kWh
|
$211
-
kW-mo/yr
|
- | - | |
| 07 | 2.1233: Analyze flue gas for proper air/fuel ratio | $6,376 | $3,000 | - | - |
$6,376
-
MMBtu
|
- | |
| 08 | 2.2442: Preheat combustion air with waste heat | $3,221 | $7,597 | - | - |
$3,221
-
MMBtu
|
- | |
| 09 | 2.2442: Preheat combustion air with waste heat | $1,810 | $3,352 | - | - |
$1,810
-
MMBtu
|
- | |
| 10 | 2.6218: Turn off equipment when not in use | $835 | - |
$835
11,083
kWh
|
- | - | - | |
| 11 | 2.7442: Keep doors and windows shut when not on use | $1,333 | - | - | - |
$1,333
-
MMBtu
|
- | |
| 12 | 2.2511: Insulate bare equipment | $1,083 | $1,584 | - | - |
$1,083
-
MMBtu
|
- | |
| 13 | 3.4116: Meter recycled water (to reduce sewer charges) | $1,400 | $422 | - | - | - |
$1,400
-
Tgal
|
|
| TOTAL RECOMMENDED | $55,567 | $71,957 |
$32,466
431,162
kWh
|
$7,878
-
kW-mo/yr
|
$13,823
-
MMBtu
|
$1,400
-
Tgal
|
||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs