ITAC Assessment: UK1512
ITAC logo
ITAC Assessment: UK1512
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2015
Principal Product Side View Mirrors
NAICS 327215: Glass Product Manufacturing Made of Purchased Glass
SIC 3714: Motor Vehicle Parts and Accessories
Sales Range $50
M
to 100
M
# of Employees 295
Plant Area 100,000
ft2
Annual Production 4,990,373
pieces
Production Hrs. Annual 7,200
hrs
Location (State) Kentucky

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $343,156 6,362,497
kWh
Electricity Demand $95,041 13,586
kW-mo/yr
Electricity Fees $110,163 -
Natural Gas $130,233 16,724
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $36,220 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $15,307

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Administrative Changes Savings Ancillary Material Cost Savings
01 2.8114: Change rate schedules or other changes in utility service $5,559 - - - $5,559 - - -
02 2.7142: Utilize higher efficiency lamps and/or ballasts $1,043 $1,215 $984
18,216
kWh
$230
-
kW-mo/yr
- - $20 $(-191.0)
03 2.7142: Utilize higher efficiency lamps and/or ballasts $3,250 $4,650 $2,353
43,585
kWh
$840
-
kW-mo/yr
- - $261 $(-204.0)
04 2.7111: Reduce illumination to minimum necessary levels $1,209 $3,940 $978
18,104
kWh
$231
-
kW-mo/yr
- - - -
05 2.7142: Utilize higher efficiency lamps and/or ballasts $3,263 $178 $1,902
35,228
kWh
$1,183
-
kW-mo/yr
- - $178 -
06 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $4,652 $1,750 $4,652
86,155
kWh
- - - - -
07 2.4224: Upgrade controls on compressors $4,297 $12,750 $2,890
53,518
kWh
$1,407
-
kW-mo/yr
- - - -
08 2.2437: Recover waste heat from equipment $5,248 $7,985 - - - $5,248
-
MMBtu
- -
09 2.2123: Insulate feedwater tank $1,278 $994 - - - $1,278
-
MMBtu
- -
10 2.1233: Analyze flue gas for proper air/fuel ratio $2,609 $1,500 - - - $2,609
-
MMBtu
- -
11 3.4116: Meter recycled water (to reduce sewer charges) $3,535 $530 - - - - $3,535 -
12 2.4221: Install compressor air intakes in coolest locations $277 $475 $277
4,201
kWh
- - - - -
TOTAL RECOMMENDED $36,220 $35,967 $14,036
259,007
kWh
$3,891
-
kW-mo/yr
$5,559 $9,135
-
MMBtu
$3,994 $(-395.0)
TOTAL IMPLEMENTED $15,307 $8,184 $5,630
104,259
kWh
$231
-
kW-mo/yr
$5,559 $3,887
-
MMBtu
- -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Administrative Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs