Assessment Year | 2015 |
---|---|
Principal Product | Side View Mirrors |
NAICS | 327215: Glass Product Manufacturing Made of Purchased Glass |
SIC | 3714: Motor Vehicle Parts and Accessories |
Sales Range | $50 M to 100M |
# of Employees | 295 |
Plant Area |
100,000
ft2
|
Annual Production | 4,990,373
pieces
|
Production Hrs. Annual | 7,200
hrs
|
Location (State) | Kentucky |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $343,156 | 6,362,497 |
kWh
|
$0.054 |
Electricity Demand | $95,041 | 13,586 |
kW-mo/yr
|
$7.00 |
Electricity Fees | $110,163 | - |
|
- |
Natural Gas | $130,233 | 16,724 |
MMBtu
|
$7.79 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $36,220 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $15,307 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.8114: Change rate schedules or other changes in utility service | $5,559 | - | - | - | $5,559 | - | - | - | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,043 | $1,215 |
$984
18,216
kWh
|
$230
-
kW-mo/yr
|
- | - | $20 | $(-191.0) | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,250 | $4,650 |
$2,353
43,585
kWh
|
$840
-
kW-mo/yr
|
- | - | $261 | $(-204.0) | |
04 | 2.7111: Reduce illumination to minimum necessary levels | $1,209 | $3,940 |
$978
18,104
kWh
|
$231
-
kW-mo/yr
|
- | - | - | - | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,263 | $178 |
$1,902
35,228
kWh
|
$1,183
-
kW-mo/yr
|
- | - | $178 | - | |
06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $4,652 | $1,750 |
$4,652
86,155
kWh
|
- | - | - | - | - | |
07 | 2.4224: Upgrade controls on compressors | $4,297 | $12,750 |
$2,890
53,518
kWh
|
$1,407
-
kW-mo/yr
|
- | - | - | - | |
08 | 2.2437: Recover waste heat from equipment | $5,248 | $7,985 | - | - | - |
$5,248
-
MMBtu
|
- | - | |
09 | 2.2123: Insulate feedwater tank | $1,278 | $994 | - | - | - |
$1,278
-
MMBtu
|
- | - | |
10 | 2.1233: Analyze flue gas for proper air/fuel ratio | $2,609 | $1,500 | - | - | - |
$2,609
-
MMBtu
|
- | - | |
11 | 3.4116: Meter recycled water (to reduce sewer charges) | $3,535 | $530 | - | - | - | - | $3,535 | - | |
12 | 2.4221: Install compressor air intakes in coolest locations | $277 | $475 |
$277
4,201
kWh
|
- | - | - | - | - | |
TOTAL RECOMMENDED | $36,220 | $35,967 |
$14,036
259,007
kWh
|
$3,891
-
kW-mo/yr
|
$5,559 |
$9,135
-
MMBtu
|
$3,994 | $(-395.0) | ||
TOTAL IMPLEMENTED | $15,307 | $8,184 |
$5,630
104,259
kWh
|
$231
-
kW-mo/yr
|
$5,559 |
$3,887
-
MMBtu
|
- | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs