| Assessment Year | 2015 |
|---|---|
| Principal Product | Fiberglass Reinforced Panels |
| NAICS | 326199: All Other Plastics Product Manufacturing |
| SIC | 3089: Plastics Products, Not Elsewhere Classified |
| Sales Range | $5 M to 10M |
| # of Employees | 109 |
| Plant Area |
103,000
ft2
|
| Annual Production | 52,000
thousand feet
|
| Production Hrs. Annual | 4,800
hrs
|
| Location (State) | Kentucky |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $161,823 | 3,352,868 |
kWh
|
$0.048 |
| Electricity Demand | $124,977 | 10,141 |
kW-mo/yr
|
$12.32 |
| Electricity Fees | $26,839 | - |
|
- |
| Natural Gas | $214,942 | 31,395 |
MMBtu
|
$6.85 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $112,244 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $112,244 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings | Water Consumption Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.7111: Reduce illumination to minimum necessary levels | $605 | $960 |
$605
11,471
kWh
|
- | - | - | - | |
| 02 | 2.7134: Use photocell controls | $3,487 | $4,040 |
$3,487
66,166
kWh
|
- | - | - | - | |
| 03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $945 | $520 |
$346
6,566
kWh
|
- | - | $599 | - | |
| 04 | 2.4224: Upgrade controls on compressors | $5,138 | $3,760 |
$2,874
54,544
kWh
|
$2,264
-
kW-mo/yr
|
- | - | - | |
| 05 | 2.4221: Install compressor air intakes in coolest locations | $2,831 | $3,000 |
$1,729
32,800
kWh
|
$1,102
-
kW-mo/yr
|
- | - | - | |
| 06 | 2.4131: Size electric motors for peak operating efficiency | $16,001 | $5,000 |
$11,727
222,526
kWh
|
$4,274
-
kW-mo/yr
|
- | - | - | |
| 07 | 2.6127: Maintain air filters by cleaning or replacement | $1,126 | $1,460 |
$1,126
21,363
kWh
|
- | - | - | - | |
| 08 | 3.4151: Minimize water usage | $556 | $2,470 | - | - | - | - |
$556
-
Tgal
|
|
| 09 | 2.2511: Insulate bare equipment | $17,159 | $9,380 | - | - |
$17,159
-
MMBtu
|
- | - | |
| 10 | 2.6218: Turn off equipment when not in use | $2,034 | $2,460 | - | - |
$2,034
-
MMBtu
|
- | - | |
| 11 | 2.2442: Preheat combustion air with waste heat | $62,362 | $45,000 | - | - |
$62,362
-
MMBtu
|
- | - | |
| TOTAL RECOMMENDED | $112,244 | $78,050 |
$21,894
415,436
kWh
|
$7,640
-
kW-mo/yr
|
$81,555
-
MMBtu
|
$599 |
$556
-
Tgal
|
||
| TOTAL IMPLEMENTED | $112,244 | $78,050 |
$21,894
415,436
kWh
|
$7,640
-
kW-mo/yr
|
$81,555
-
MMBtu
|
$599 |
$556
-
Tgal
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings | Water Consumption Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs