| Assessment Year | 2013 |
|---|---|
| Principal Product | Oral Solid Dosage Drugs |
| NAICS | 325412: Pharmaceutical Preparation Manufacturing |
| SIC | 2834: Pharmaceutical Preparations |
| Sales Range | $100 M to 500M |
| # of Employees | 400 |
| Plant Area |
100,000
ft2
|
| Annual Production | 440,925
lb
|
| Production Hrs. Annual | 8,400
hrs
|
| Location (State) | Kentucky |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $490,313 | 14,067,000 |
kWh
|
$0.035 |
| Electricity Demand | $356,979 | 27,598 |
kW-mo/yr
|
$12.93 |
| Electricity Fees | $131,240 | - |
|
- |
| Natural Gas | $343,978 | 71,099 |
MMBtu
|
$4.84 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $191,185 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $154,048 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.2437: Recover waste heat from equipment | $139,142 | $342,000 |
$49,934
1,430,768
kWh
|
$26,439
-
kW-mo/yr
|
- |
$62,769
-
MMBtu
|
|
| 02 | 2.3212: Optimize plant power factor | $11,706 | $17,700 | - | - | $11,706 | - | |
| 03 | 2.4224: Upgrade controls on compressors | $15,719 | $35,000 |
$15,719
450,398
kWh
|
- | - | - | |
| 04 | 3.1161: Eliminate/reduce an operation | $12,899 | - |
$12,899
369,600
kWh
|
- | - | - | |
| 05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $8,519 | - |
$5,570
159,600
kWh
|
$2,949
-
kW-mo/yr
|
- | - | |
| 06 | 2.7211: Clean and maintain refrigerant condensers and towers | $3,200 | $1,900 |
$3,200
92,490
kWh
|
- | - | - | |
| TOTAL RECOMMENDED | $191,185 | $396,600 |
$87,322
2,502,856
kWh
|
$29,388
-
kW-mo/yr
|
$11,706 |
$62,769
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $154,048 | $361,600 |
$53,134
1,523,258
kWh
|
$26,439
-
kW-mo/yr
|
$11,706 |
$62,769
-
MMBtu
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs