Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2013
Principal Product Grain drying and handling
NAICS 493110: General Warehousing and Storage
SIC 5153: Grain and Field Beans
Sales Range $100
M
to 500
M
# of Employees 100
Plant Area 8,000
ft2
Annual Production 1,000,000
ton
Production Hrs. Annual 2,600
hrs
Location (State) Indiana

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $233,139 3,267,629
kWh
Electricity Demand $2,954 14,079
kW-mo/yr
Electricity Fees $4,679 -
Natural Gas $63,242 11,126
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $11,772 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $7,523

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Fees Savings Natural Gas Savings
01 2.4222: Install adequate dryers on air lines to eliminate blowdown $4,249 $2,200 $4,249
49,809
kWh
- -
02 2.4111: Utilize energy-efficient belts and other improved mechanisms $1,824 $4,516 $1,824
21,379
kWh
- -
03 2.6124: Establish equipment maintenance schedule $4,021 $1,610 $796
9,335
kWh
- $3,225
-
MMBtu
04 2.8123: Pay utility bills on time $1,678 - - $1,678 -
TOTAL RECOMMENDED $11,772 $8,326 $6,869
80,523
kWh
$1,678 $3,225
-
MMBtu
TOTAL IMPLEMENTED $7,523 $6,126 $2,620
30,714
kWh
$1,678 $3,225
-
MMBtu
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs