ITAC Assessment: MUCM34
ITAC logo
ITAC Assessment: MUCM34
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2025
Principal Product Beer
NAICS 312120: Breweries
SIC 2082: Malt Beverages
Sales Range $5
M
to 10
M
# of Employees 38
Plant Area 25,000
ft2
Annual Production 480,500
units
Production Hrs. Annual 3,120
hrs
Location (State) Michigan

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $75,973 534,764
kWh
Natural Gas $27,274 3,514
MMBtu
Other Gas $1,678 1
MMBtu
Waste Disposal Costs
Water Usage $17,175 2
Tgal
TOTAL YEARLY COSTS $122,100
RECOMMENDED SAVINGS* $3,448 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
01 2.2113: Repair or replace steam traps $607 $342 - $607
-
MMBtu
-
02 2.7135: Install occupancy sensors $527 $468 $527
3,710
kWh
- -
03 2.7142: Utilize higher efficiency lamps and/or ballasts $894 $2,471 $894
6,295
kWh
- -
04 2.7224: Reduce space conditioning during non-working hours $1,379 - $1,017
7,158
kWh
$362
-
MMBtu
-
05 4.821: Pay bills on time to avoid late fees $41 - - - $41
TOTAL RECOMMENDED $3,448 $3,281 $2,438
17,164
kWh
$969
-
MMBtu
$41
TOTAL IMPLEMENTED - - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs