| Assessment Year | 2026 |
|---|---|
| Principal Product | Engine Blades |
| NAICS | 336412: Aircraft Engine and Engine Parts Manufacturing |
| SIC | 3724: Aircraft Engines and Engine Parts |
| Sales Range | $100 M to 500M |
| # of Employees | 80 |
| Plant Area |
30,000
ft2
|
| Annual Production | 20,000
units
|
| Production Hrs. Annual | 8,760
hrs
|
| Location (State) | Florida |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $139,430 | 2,725,464 |
kWh
|
$0.051 |
| Electricity Demand | $142,874 | 6,312 |
kW-mo/yr
|
$22.64 |
| Electricity Fees | $50,805 | - |
|
- |
| TOTAL YEARLY COSTS | $333,109 | |||
| RECOMMENDED SAVINGS* | $222,949 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.9114: Use solar heat to make electricty | $97,535 | $375,213 |
$36,420
714,109
kWh
|
$61,115
-
kW-mo/yr
|
- | - | |
| 02 | 2.4133: Use most efficient type of electric motors | $27,587 | $20,669 |
$7,531
147,670
kWh
|
$20,056
-
kW-mo/yr
|
- | - | |
| 03 | 2.3191: Use demand controller or load shedder | $19,731 | $14,663 |
$9,730
190,782
kWh
|
$10,001
-
kW-mo/yr
|
- | - | |
| 04 | 2.4112: Install soft-start to eliminate nuisance trips | $5,657 | $8,456 |
$5,657
110,920
kWh
|
- | - | - | |
| 05 | 2.6231: Utilize controls to operate equipment only when needed | $2,780 | $7,500 |
$2,780
54,509
kWh
|
- | - | - | |
| 06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,900 | - |
$1,900
37,255
kWh
|
- | - | - | |
| 07 | 2.4231: Reduce the pressure of compressed air to the minimum required | $770 | - |
$770
15,107
kWh
|
- | - | - | |
| 08 | 2.4237: Substitute compressed air cooling with water or air cooling | $631 | $2,700 |
$631
12,365
kWh
|
- | - | - | |
| 09 | 4.448: Install automatic part storage / retreval system | $16,655 | $75,000 | - | - | - | $16,655 | |
| 10 | 4.424: Improve space comfort conditioning | $45,534 | $22,638 |
$(-1,398.0)
(-27,404)
kWh
|
$(-2,863.0)
-
kW-mo/yr
|
$49,795 | - | |
| 11 | 4.663: Level two – install control system using iiot devices with communication capabilities to store data to the cloud | $4,169 | $15,000 |
$4,169
81,754
kWh
|
- | - | - | |
| TOTAL RECOMMENDED | $222,949 | $541,839 |
$68,190
1,337,067
kWh
|
$88,309
-
kW-mo/yr
|
$49,795 | $16,655 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs