| Assessment Year | 2026 |
|---|---|
| Principal Product | Welding and Cutting Products |
| NAICS | 333611: Turbine and Turbine Generator Set Units Manufacturing |
| SIC | 3511: Steam, Gas, and Hydraulic Turbines, and Turbine Generator Set Units |
| Sales Range | $10 M to 50M |
| # of Employees | 120 |
| Plant Area |
72,000
ft2
|
| Annual Production | 10,000,000
units
|
| Production Hrs. Annual | 4,160
hrs
|
| Location (State) | Florida |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $139,487 | 2,283,531 |
kWh
|
$0.061 |
| Electricity Demand | $79,044 | 5,901 |
kW-mo/yr
|
$13.40 |
| Electricity Fees | $12,663 | - |
|
- |
| TOTAL YEARLY COSTS | $231,194 | |||
| RECOMMENDED SAVINGS* | $96,472 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.3191: Use demand controller or load shedder | $15,284 | $12,285 |
$9,751
159,847
kWh
|
$5,533
-
kW-mo/yr
|
- | |
| 02 | 2.6231: Utilize controls to operate equipment only when needed | $10,771 | $25,570 |
$10,771
176,572
kWh
|
- | - | |
| 03 | 2.7132: Install timers on light switches in little used areas | $4,803 | $20,000 |
$4,803
78,744
kWh
|
- | - | |
| 04 | 2.2623: Minimize condenser cooling water temperature | $4,516 | $6,528 |
$4,516
74,040
kWh
|
- | - | |
| 05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,638 | - |
$1,638
26,856
kWh
|
- | - | |
| 06 | 2.2414: Use waste heat from hot flue gases to preheat | $1,294 | $1,610 |
$1,294
21,219
kWh
|
- | - | |
| 07 | 2.7132: Install timers on light switches in little used areas | $820 | $315 |
$820
13,440
kWh
|
- | - | |
| 08 | 4.652: Replace existing equipment with more suitable substitutes | $28,500 | $1,912 | - | - | $28,500 | |
| 09 | 4.424: Improve space comfort conditioning | $28,846 | $31,213 |
$(-12,650.0)
(-69,142)
kWh
|
- | $41,496 | |
| TOTAL RECOMMENDED | $96,472 | $99,433 |
$20,943
481,576
kWh
|
$5,533
-
kW-mo/yr
|
$69,996 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs