ITAC Assessment: UF0636
ITAC logo
ITAC Assessment: UF0636
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2025
Principal Product Many varieties of bread
NAICS 311812: Commercial Bakeries
SIC 2051: Bread and Other Bakery Products, Except Cookies and Crackers
Sales Range $100
M
to 500
M
# of Employees 352
Plant Area 300,000
ft2
Annual Production 1,700,000,000
units
Production Hrs. Annual 8,760
hrs
Location (State) Florida

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $456,070 8,831,200
kWh
Electricity Demand $208,221 13,627
kW-mo/yr
Electricity Fees $193,158 -
Natural Gas $445,391 55,277
MMBtu
Waste Disposal Costs
Water Usage $82,835 9,575
Tgal
Water Disposal $75,350 9,575
Tgal
TOTAL YEARLY COSTS $1,461,025
RECOMMENDED SAVINGS* $841,854 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Administrative Changes Savings Ancillary Material Cost Savings
01 2.3417: Use waste heat with a closed-cycle gas turbine-generator set to cogenerate electricity and heat $569,031 $1,748,460 $471,421
9,065,800
kWh
$208,297
-
kW-mo/yr
$(-12,991.0)
-
MMBtu
- $(-97,696.0) -
02 2.3191: Use demand controller or load shedder $46,721 $47,512 $32,146
618,184
kWh
$14,575
-
kW-mo/yr
- - - -
03 2.4133: Use most efficient type of electric motors $37,528 $29,400 $26,757
514,562
kWh
$10,771
-
kW-mo/yr
- - - -
04 2.7142: Utilize higher efficiency lamps and/or ballasts $14,820 $29,969 $10,559
203,065
kWh
$4,261
-
kW-mo/yr
- - - -
05 2.6231: Utilize controls to operate equipment only when needed $7,674 $25,280 $7,674
147,580
kWh
- - - - -
06 2.4231: Reduce the pressure of compressed air to the minimum required $7,364 - $7,364
141,624
kWh
- - - - -
07 2.1222: Install turbulators $4,892 $7,500 - - $4,892
-
MMBtu
- - -
08 2.1116: Improve combustion control capability $4,064 $2,800 - - $4,064
-
MMBtu
- - -
09 2.4111: Utilize energy-efficient belts and other improved mechanisms $2,852 - $2,695
51,830
kWh
- - $84 - $73
10 4.661: Level zero – install control systems for existing equipment $45,922 $60,000 $45,922
883,120
kWh
- - - - -
11 4.652: Replace existing equipment with more suitable substitutes $29,400 $2,792 - - - - $29,400 -
12 3.4116: Meter recycled water (to reduce sewer charges) $71,586 $4,000 - - - - $71,586 -
TOTAL RECOMMENDED $841,854 $1,957,713 $604,538
11,625,765
kWh
$237,904
-
kW-mo/yr
$(-4,035.0)
-
MMBtu
$84 $3,290 $73
TOTAL IMPLEMENTED - - - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Administrative Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs