ITAC Assessment: UF0634
ITAC logo
ITAC Assessment: UF0634
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2025
Principal Product Custom Parts Fabrication
NAICS 332999: All Other Miscellaneous Fabricated Metal Product Manufacturing
SIC 3499: Fabricated Metal Products, Not Elsewhere Classified
Sales Range $5
M
to 10
M
# of Employees 17
Plant Area 16,858
ft2
Annual Production 72,607
units
Production Hrs. Annual 2,210
hrs
Location (State) Florida

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $19,584 311,680
kWh
Electricity Demand $9,463 1,047
kW-mo/yr
Electricity Fees $3,244 -
Other Gas $31,521 319
MMBtu
Other Energy $42,839 2,702
MMBtu
TOTAL YEARLY COSTS $106,651
RECOMMENDED SAVINGS* $108,246 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Other Energy Savings Personnel Changes Savings Administrative Changes Savings
01 2.7243: Improve air circulation with destratification fans / other methods $45,476 $12,413 $(-575.0)
(-9,126)
kWh
$(-381.0)
-
kW-mo/yr
- $46,432 -
02 2.4322: Use or replace with energy efficient substitutes $19,463 $60,000 $(-13,140.0)
(-208,571)
kWh
$(-10,236.0)
-
kW-mo/yr
$42,839
-
MMBtu
- -
03 2.7142: Utilize higher efficiency lamps and/or ballasts $8,705 $4,689 $6,006
95,333
kWh
$2,699
-
kW-mo/yr
- - -
04 2.4226: Use / purchase optimum sized compressor $9,396 $25,300 $2,161
34,296
kWh
$2,235
-
kW-mo/yr
- - $5,000
05 2.3191: Use demand controller or load shedder $2,037 $1,677 $1,375
21,818
kWh
$662
-
kW-mo/yr
- - -
06 2.4239: Eliminate or reduce compressed air usage $583 - $583
9,253
kWh
- - - -
07 2.4224: Upgrade controls on compressors $326 $1,500 $326
5,182
kWh
- - - -
08 4.424: Improve space comfort conditioning $22,260 $2,620 $(-575.0)
(-9,126)
kWh
$(-381.0)
-
kW-mo/yr
- $23,216 -
TOTAL RECOMMENDED $108,246 $108,199 $(-3,839.0)
(-60,941)
kWh
$(-5,402.0)
-
kW-mo/yr
$42,839
-
MMBtu
$69,648 $5,000
TOTAL IMPLEMENTED - - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Other Energy Savings Personnel Changes Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs