| Assessment Year | 2025 |
|---|---|
| Principal Product | Citrus Flavor and Fragrance Ingredients |
| NAICS | 325199: All Other Basic Organic Chemical Manufacturing |
| SIC | 2869: Industrial Organic Chemicals, Not Elsewhere Classified |
| Sales Range | $10 M to 50M |
| # of Employees | 90 |
| Plant Area |
103,000
ft2
|
| Annual Production | 7,500
ton
|
| Production Hrs. Annual | 8,760
hrs
|
| Location (State) | Florida |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $160,812 | 3,755,009 |
kWh
|
$0.043 | |
| Electricity Demand | $149,563 | 8,576 |
kW-mo/yr
|
$17.44 | |
| Electricity Fees | $54,783 | - |
|
- | |
| Natural Gas | $210,000 | 19,000 |
MMBtu
|
$11.05 | |
| LPG | $9,560 | 218 |
MMBtu
|
$43.77 | |
| Waste Disposal Costs | |||||
| Water Usage | $22,962 | 276 |
Tgal
|
$83.20 | |
| Water Disposal | $38,436 | 3,655 |
Tgal
|
$10.52 | |
| TOTAL YEARLY COSTS | $646,116 | ||||
| RECOMMENDED SAVINGS* | $131,544 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | - | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.9114: Use solar heat to make electricty | $43,631 | $322,608 |
$26,889
625,327
kWh
|
$16,742
-
kW-mo/yr
|
- | |
| 02 | 2.3191: Use demand controller or load shedder | $21,772 | $20,202 |
$11,302
262,851
kWh
|
$10,470
-
kW-mo/yr
|
- | |
| 03 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $16,911 | $34,076 |
$16,911
393,271
kWh
|
- | - | |
| 04 | 2.2414: Use waste heat from hot flue gases to preheat | $12,726 | $12,000 | - | - |
$12,726
-
MMBtu
|
|
| 05 | 2.6231: Utilize controls to operate equipment only when needed | $5,526 | $20,560 |
$5,526
128,501
kWh
|
- | - | |
| 06 | 2.1116: Improve combustion control capability | $4,200 | $2,000 | - | - |
$4,200
-
MMBtu
|
|
| 07 | 2.2623: Minimize condenser cooling water temperature | $4,170 | $6,785 |
$4,170
96,980
kWh
|
- | - | |
| 08 | 2.4231: Reduce the pressure of compressed air to the minimum required | $4,170 | $2,654 |
$4,170
97,980
kWh
|
- | - | |
| 09 | 2.1222: Install turbulators | $2,277 | $3,750 | - | - |
$2,277
-
MMBtu
|
|
| 10 | 2.2124: Install de-aerator in place of condensate tank | $2,684 | $2,743 | - | - |
$2,684
-
MMBtu
|
|
| 11 | 3.3132: Use reverse osmosis to concentrate material | $3,839 | $3,079 | - | - |
$3,839
-
MMBtu
|
|
| 12 | 4.661: Level zero – install control systems for existing equipment | $7,429 | $20,000 |
$3,229
75,100
kWh
|
- |
$4,200
-
MMBtu
|
|
| 13 | 4.662: Level one – add communication using iiot devices to existing control system to modify operations | $1,094 | - |
$663
15,432
kWh
|
- |
$431
-
MMBtu
|
|
| 14 | 4.424: Improve space comfort conditioning | $1,115 | $3,888 |
$1,115
25,920
kWh
|
- | - | |
| TOTAL RECOMMENDED | $131,544 | $454,345 |
$73,975
1,721,362
kWh
|
$27,212
-
kW-mo/yr
|
$30,357
-
MMBtu
|
||
| TOTAL IMPLEMENTED | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs