Assessment Year | 2025 |
---|---|
Principal Product | Plastic Bottle Caps |
NAICS | 325211: Plastics Material and Resin Manufacturing |
SIC | 2353: Hats, Caps, and Millinery |
Sales Range | $10 M to 50M |
# of Employees | 53 |
Plant Area |
86,000
ft2
|
Annual Production | 2,255,400,000
units
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Florida |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $551,813 | 8,161,649 |
kWh
|
$0.068 |
Electricity Demand | $65,814 | 17,271 |
kW-mo/yr
|
$3.81 |
Electricity Fees | $46,080 | - |
|
- |
TOTAL YEARLY COSTS | $663,707 | |||
RECOMMENDED SAVINGS* | $275,123 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.9114: Use solar heat to make electricty | $45,801 | $322,608 |
$42,142
619,742
kWh
|
$3,659
-
kW-mo/yr
|
- | |
02 | 2.3191: Use demand controller or load shedder | $43,459 | $43,906 |
$38,849
571,315
kWh
|
$4,610
-
kW-mo/yr
|
- | |
03 | 2.6231: Utilize controls to operate equipment only when needed | $12,464 | $25,640 |
$10,064
147,996
kWh
|
$2,400
-
kW-mo/yr
|
- | |
04 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $10,671 | $41,856 |
$10,671
156,931
kWh
|
- | - | |
05 | 2.4321: Upgrade obsolete equipment | $4,580 | $16,608 |
$4,921
72,362
kWh
|
$(-341.0)
-
kW-mo/yr
|
- | |
06 | 2.4239: Eliminate or reduce compressed air usage | $3,938 | - |
$3,938
57,908
kWh
|
- | - | |
07 | 2.2623: Minimize condenser cooling water temperature | $3,937 | $18,930 |
$3,937
57,908
kWh
|
- | - | |
08 | 2.4224: Upgrade controls on compressors | $2,783 | $6,000 |
$2,783
40,927
kWh
|
- | - | |
09 | 2.7243: Improve air circulation with destratification fans / other methods | $1,115 | $1,235 |
$1,115
16,992
kWh
|
- | - | |
10 | 2.4221: Install compressor air intakes in coolest locations | $514 | $1,235 |
$514
7,560
kWh
|
- | - | |
11 | 4.424: Improve space comfort conditioning | $141,216 | $3,660 |
$(-3,699.0)
(-54,400)
kWh
|
$(-321.0)
-
kW-mo/yr
|
$145,236 | |
12 | 4.424: Improve space comfort conditioning | $4,645 | $1,476 |
$4,645
68,302
kWh
|
- | - | |
TOTAL RECOMMENDED | $275,123 | $483,154 |
$119,880
1,763,543
kWh
|
$10,007
-
kW-mo/yr
|
$145,236 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs