ITAC Assessment: UF0617
ITAC logo
ITAC Assessment: UF0617
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2024
Principal Product Healthcare Education Tools
NAICS 333249: Other Industrial Machinery Manufacturing
SIC 3559: Special Industry Machinery, Not Elsewhere Classified
Sales Range $50
M
to 100
M
# of Employees 364
Plant Area 96,138
ft2
Annual Production 1,800
units
Production Hrs. Annual 2,730
hrs
Location (State) Florida

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $67,050 981,480
kWh
Electricity Demand $36,538 2,915
kW-mo/yr
Electricity Fees $17,609 -
TOTAL YEARLY COSTS $121,197
RECOMMENDED SAVINGS* $1,081,701 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Personnel Changes Savings Administrative Changes Savings
01 2.9114: Use solar heat to make electricty $83,700 $322,608 $43,591
641,049
kWh
$40,109
-
kW-mo/yr
- -
02 2.7243: Improve air circulation with destratification fans / other methods $13,015 $12,416 $4,557
67,020
kWh
$(-528.0)
-
kW-mo/yr
$8,986 -
03 2.7232: Replace existing hvac unit with high efficiency model $10,599 $49,000 $7,744
113,880
kWh
$2,855
-
kW-mo/yr
- -
04 2.3191: Use demand controller or load shedder $7,230 $5,280 $4,672
68,704
kWh
$2,558
-
kW-mo/yr
- -
05 2.7421: Reduce glazed areas in buildings $1,046 $1,720 $1,046
15,320
kWh
- - -
06 4.721: Initiate a program to acquire iso certification $890,327 $117,000 $6,674
98,148
kWh
$3,653
-
kW-mo/yr
- $880,000
07 4.446: Automate finishing process $74,880 $100,000 - - $74,880 -
08 4.424: Improve space comfort conditioning $904 $1,752 $1,432
21,059
kWh
$(-528.0)
-
kW-mo/yr
- -
TOTAL RECOMMENDED $1,081,701 $609,776 $69,716
1,025,180
kWh
$48,119
-
kW-mo/yr
$83,866 $880,000
TOTAL IMPLEMENTED - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Personnel Changes Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs