| Assessment Year | 2024 |
|---|---|
| Principal Product | Precision Cutting Tools |
| NAICS | 333249: Other Industrial Machinery Manufacturing |
| SIC | 3559: Special Industry Machinery, Not Elsewhere Classified |
| Sales Range | $10 M to 50M |
| # of Employees | 50 |
| Plant Area |
37,000
ft2
|
| Annual Production | 2,300,880
units
|
| Production Hrs. Annual | 6,188
hrs
|
| Location (State) | Florida |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $313,255 | 3,407,653 |
kWh
|
$0.092 |
| Electricity Demand | $99,108 | 7,701 |
kW-mo/yr
|
$12.87 |
| Electricity Fees | $70,979 | - |
|
- |
| TOTAL YEARLY COSTS | $483,342 | |||
| RECOMMENDED SAVINGS* | $256,378 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $229,522 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.9114: Use solar heat to make electricty | $108,899 | $322,608 |
$59,482
646,542
kWh
|
$49,417
-
kW-mo/yr
|
- | - | |
| 02 | 2.3191: Use demand controller or load shedder | $28,883 | $18,333 |
$21,945
238,536
kWh
|
$6,938
-
kW-mo/yr
|
- | - | |
| 03 | 2.6231: Utilize controls to operate equipment only when needed | $24,012 | $25,400 |
$24,012
261,006
kWh
|
- | - | - | |
| 04 | 2.2622: Replace existing chiller with high efficiency model | $9,119 | $36,000 |
$5,456
59,300
kWh
|
$3,663
-
kW-mo/yr
|
- | - | |
| 05 | 2.7135: Install occupancy sensors | $4,345 | $2,330 |
$4,345
47,232
kWh
|
- | - | - | |
| 06 | 2.4112: Install soft-start to eliminate nuisance trips | $2,691 | $5,108 |
$2,691
29,275
kWh
|
- | - | - | |
| 07 | 2.4231: Reduce the pressure of compressed air to the minimum required | $2,062 | $7,200 |
$2,062
22,409
kWh
|
- | - | - | |
| 08 | 2.4224: Upgrade controls on compressors | $1,315 | $4,000 |
$1,315
14,292
kWh
|
- | - | - | |
| 09 | 4.662: Level one – add communication using iiot devices to existing control system to modify operations | $54,895 | - | - | - | - | $54,895 | |
| 10 | 4.661: Level zero – install control systems for existing equipment | $15,675 | $25,000 |
$15,675
170,383
kWh
|
- | - | - | |
| 11 | 4.631: Install an uninteruptable power supply | $4,482 | $3,330 | - | - | $4,482 | - | |
| TOTAL RECOMMENDED | $256,378 | $449,309 |
$136,983
1,488,975
kWh
|
$60,018
-
kW-mo/yr
|
$4,482 | $54,895 | ||
| TOTAL IMPLEMENTED | $229,522 | $381,109 |
$113,790
1,236,883
kWh
|
$56,355
-
kW-mo/yr
|
$4,482 | $54,895 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Administrative Changes Savings | Ancillary Material Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs